Final | 12/4/2000 | 12/4/2000 | 12/4/2000 | A | PASS |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 12/04/2000 at 07:14:21. Contact: .
|
Final | 12/1/2000 | 12/1/2000 | 12/1/2000 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 12/01/2000 at 10:36:46. Contact: . set all equipment 12/1/2000 2:31:31 PM
|
Final | 11/30/2000 | 11/30/2000 | 11/30/2000 | P | FAIL |
Bill VanDegrift
|
|
|
###-#### dcva required at juice, coffee stations, test all bfp, airgap required on ice bin drain 11/30/2000 2:39:10 PM
|
Final | 11/15/2000 | 11/15/2000 | 11/15/2000 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 11/15/2000 at 07:21:01. Contact: ###-####. final conference ok, needs to test backflow preventors, unions at backflow preventors and set the equipment 11/15/2000 3:45:07 PM
|
Plumbing Rough-in | 10/23/2000 | 10/24/2000 | 10/24/2000 | A | PASS |
Bill VanDegrift
|
|
|
Rock ###-####
|
Water and/or Sewer | 9/12/2000 | 9/13/2000 | 9/13/2000 | A | PART |
Bill VanDegrift
|
|
|
water line from bld to street-up to meter-elliott-- ###-####
|
Water and/or Sewer | 8/29/2000 | 8/29/2000 | 8/29/2000 | P | PART |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 8/29/2000
|
Water and/or Sewer | 8/29/2000 | 8/29/2000 | 8/29/2000 | P | PART |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 8/29/2000 partial w/l
|
Water and/or Sewer | 8/29/2000 | 8/29/2000 | 8/29/2000 | P | PART |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 8/29/2000
|
Groundwork | 8/24/2000 | 8/24/2000 | 8/24/2000 | A | PASS |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 8/24/2000 gw ok just needs water service
|
Plumbing Rough-in | 8/24/2000 | 8/24/2000 | 8/24/2000 | P | PART |
Bill VanDegrift
|
|
|
rock-- ###-#### cell-- r/i --under slab
|