Final | 3/8/2002 | 3/8/2002 | 3/8/2002 | P | PASS |
Bill VanDegrift
|
|
|
john ###-#### fn
|
Final | 12/27/2001 | 12/27/2001 | 12/27/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 12/27/2001 at 07:40:29. Contact: ###-####. temp occ ok 12/27/2001 3:10:03 PM
|
Final | 10/27/2001 | 10/29/2001 | 10/29/2001 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 10/27/2001 at 14:27:47. Contact: ###-####. temp ok for rm t.i. ymc needs to get cleared before card is signed. 10/29/2001 12:00:10 PM
|
Final | 10/25/2001 | 10/25/2001 | 10/25/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 10/25/2001 at 08:10:32. Contact: ###-####. temp occok 10/25/2001 4:59:56 PM
|
Roof Drains | 10/3/2001 | 10/3/2001 | 10/3/2001 | P | PASS |
Lee Rice
|
|
|
Scheduled by a contractor via Hello! on 10/03/2001 at 12:00:19. Contact: ###-####.
|
Groundwork | 9/18/2001 | 9/18/2001 | 9/18/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 09/18/2001 at 09:25:44. Contact: ###-####. emergency shower in chemical loading dock underground water test ok 9/18/2001 2:04:21 PM
|
Groundwork | 8/27/2001 | 8/27/2001 | 8/27/2001 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 08/27/2001 at 07:09:03. Contact: ###-####. 200 feet of outside 4-inch sewer line ok two halh inch water lines for drinking fountains ok two 4-inch vent's through roof test ok 8/27/2001 12:55:48 PM
|
Plumbing Rough-in | 8/22/2001 | 8/22/2001 | 8/22/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 08/22/2001 at 11:10:08. Contact: ###-####. gw ok 8/22/2001 2:15:40 PM
|
Plumbing Rough-in | 6/28/2001 | 6/29/2001 | 6/29/2001 | A | PART |
Lee Rice
|
|
|
Scheduled by a contractor via Hello! on 06/28/2001 at 16:04:55. Contact: ###-####.bathroom ok 6/29/2001 12:36:12 PM
|
Storm Drains | 6/26/2001 | 6/26/2001 | 6/26/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 06/26/2001 at 11:25:28. Contact: ###-####. south east loading dock to roof test ok 6/26/2001 3:43:19 PM
|
Roof Drains | 6/11/2001 | 6/11/2001 | 6/11/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 06/11/2001 at 11:05:28. Contact: ###-####. rd center west test ok 6/11/2001 2:50:42 PM
|
Groundwork | 6/8/2001 | 6/8/2001 | 6/8/2001 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 06/08/2001 at 06:02:37. Contact: ###-####. f.d. s.d. in fire riser room n.e corner 6/8/2001 9:29:43 AM
|
Groundwork | 6/4/2001 | 6/5/2001 | 6/5/2001 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 06/04/2001 at 15:11:51. Contact: ###-####. water service north east, drinking fountain waste and vent piping 6/5/2001 1:50:17 PM
|
Groundwork | 5/24/2001 | 5/24/2001 | 5/24/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 05/24/2001 at 07:46:40. Contact: ###-#### 8" sd stub s.e. corner 5/24/2001 2:27:07 PM
|
Groundwork | 5/18/2001 | 5/18/2001 | 5/18/2001 | P | PART |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 5/18/2001 3:21:12 PM dlb containment in loading dock
|
Groundwork | 5/4/2001 | 5/4/2001 | 5/4/2001 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 05/04/2001 at 06:14:12. Contact: ###-####. 8" rd east side center ok 5/4/2001 3:54:37 PM
|
Groundwork | 5/4/2001 | 5/4/2001 | 5/4/2001 | P | PART |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 5/4/2001 3:55:22 PM sewer stubed out an additional 15' test ok
|
Roof Drains | 5/2/2001 | 5/2/2001 | 5/2/2001 | P | CANC |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 05/02/2001 at 08:23:53. Contact: ###-####.
|
Roof Drains | 5/1/2001 | 5/1/2001 | 5/1/2001 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 05/01/2001 at 06:13:31. Contact: ###-####. 2 sets of rd east side 1 am 1 pm 5/1/2001 4:56:59 PM
|
Groundwork | 4/30/2001 | 4/30/2001 | 4/30/2001 | A | FAIL |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 04/30/2001 at 06:09:09. Contact: ###-####. test wouldnt hold 4/30/2001 2:15:29 PM
|
Groundwork | 4/30/2001 | 4/30/2001 | 4/30/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 04/30/2001 at 11:23:08. Contact: ###-####. 6" sewer stub from basment, 4" drain in south fire riser room west side 4/30/2001 4:08:13 PM
|
Plumbing Rough-in | 4/26/2001 | 4/27/2001 | 4/27/2001 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 04/26/2001 at 13:12:45. Contact: ###-####. west rd center 8" roof to 2' below fan deck ceiling 4/26/2001 4:00:36 PM
|
Roof Drains | 4/27/2001 | 4/27/2001 | 4/27/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 04/27/2001 at 07:38:57. Contact: ###-####. 2 more rd's, west end 4/27/2001 4:08:21 PM
|
Plumbing Rough-in | 4/25/2001 | 4/25/2001 | 4/25/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 04/25/2001 at 10:29:19. Contact: ###-####. 8" rd west side from roof to 10' above fab deck, 4" rd from roof thru fab deck to exterior 4/25/2001 4:20:14 PM
|
Plumbing Rough-in | 4/24/2001 | 4/24/2001 | 4/24/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 04/24/2001 at 10:29:18. Contact: ###-####. 8" rd south west end roof to exteior 4/24/2001 5:05:56 PM
|
Groundwork | 4/23/2001 | 4/23/2001 | 4/23/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 04/23/2001 at 07:12:22. Contact: ###-####. north fan deck of test ok rd test failed, rd and fd in and over fire riser room test ok 4/23/2001 4:41:55 PM
|
Groundwork | 4/20/2001 | 4/20/2001 | 4/20/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 04/20/2001 at 11:11:46. Contact: ###-####. water service test ok 4/20/2001 4:20:10 PM
|
Groundwork | 4/19/2001 | 4/19/2001 | 4/19/2001 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 04/19/2001 at 06:21:48. Contact: ###-####. under ground piping and roof drain at grid line k1 and 30 test ok 4/19/2001 4:21:56 PM
|
Water and/or Sewer | 4/12/2001 | 4/13/2001 | 4/13/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by Inspector: 330 On 4/12/2001 2:22:14 PM ###-#### 8" ductile iron water main stub out the building, test ok 4/13/2001 2:43:51 PM
|
Groundwork | 4/12/2001 | 4/12/2001 | 4/12/2001 | P | CANC |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 04/12/2001 at 06:45:06. Contact: ###-####.
|
Groundwork | 4/6/2001 | 4/6/2001 | 4/6/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 04/06/2001 at 06:18:59. Contact: ###-####. rd extention outside 4/6/2001 4:50:54 PM
|
Groundwork | 3/15/2001 | 3/16/2001 | 3/16/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 03/15/2001 at 17:39:40. Contact: ###-####. one section dlb cont piping from area 1 se to area 3 ne ok 3/16/2001 3:07:08 PM
|
Groundwork | 2/8/2001 | 2/9/2001 | 2/9/2001 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 02/08/2001 at 18:34:49. Contact: ###-####. 4" waste line thru wall with riser to floor drain in fire riser room. 2/9/2001 11:44:48 AM
|
Groundwork | 2/7/2001 | 2/8/2001 | 2/8/2001 | A | CANC |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 02/07/2001 at 12:10:12. Contact: ###-####.
|
Storm Drains | 2/5/2001 | 2/6/2001 | 2/6/2001 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 02/05/2001 at 13:05:40. Contact: ###-####. rd stubout at col 24 ok 2/6/2001 11:26:57 AM
|
Plumbing Rough-in | 2/5/2001 | 2/5/2001 | 2/5/2001 | P | PART |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 2/5/2001 5:27:26 PM rain drain stub out and up at col. 24 west side
|
Groundwork | 12/20/2000 | 12/21/2000 | 12/20/2000 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 12/20/2000 at 11:59:48. Contact: ###-####. trench drain to basement north west corner 12/20/2000 2:46:40 PM
|
Groundwork | 12/13/2000 | 12/13/2000 | 12/13/2000 | P | PART |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 12/13/2000 test on restroom group ok
|
Plumbing Rough-in | 12/12/2000 | 12/13/2000 | 12/13/2000 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 12/12/2000 at 15:39:19. Contact: ###-####. piping complete for restroom but the test droped of a little 12/13/2000 11:25:30 AM
|
Plumbing Rough-in | 12/12/2000 | 12/12/2000 | 12/12/2000 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 12/12/2000 at 10:05:45. Contact: ###-####. partial restroom in sub fab 12/12/2000 3:44:08 PM
|
Groundwork | 11/6/2000 | 11/6/2000 | 11/6/2000 | P | PART |
Bill VanDegrift
|
|
|
###-#### or ###-#### last dlb containment on basement ok 11/6/2000 4:40:42 PM
|
Plumbing Rough-in | 9/21/2000 | 9/22/2000 | 9/22/2000 | A | PART |
Bill VanDegrift
|
|
|
LANE ###-#### R/I 4" to ejector 9/22/2000 7:44:45 AM
|