Final | 12/28/2000 | 12/28/2000 | 12/28/2000 | P | PASS |
Gary Ziegler
|
|
|
Scheduled by a contractor via Hello! on 12/28/2000 at 10:14:52. Contact: ###-####.
|
Plumbing Rough-in | 11/15/2000 | 11/15/2000 | 11/15/2000 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 11/15/2000 at 10:42:39. Contact: ###-####.gary inspected on 11-14-00 11/16/2000 12:30:23 PM
|
Plumbing Rough-in | 11/13/2000 | 11/13/2000 | 11/13/2000 | P | PASS |
Gary Ziegler
|
|
|
Scheduled by a contractor via Hello! on 11/13/2000 at 08:32:41. Contact: ###-####.
|
Plumbing Rough-in | 11/13/2000 | 11/13/2000 | 11/13/2000 | P | CANC |
Gary Ziegler
|
|
|
Scheduled by a contractor via Hello! on 11/13/2000 at 08:32:41. Contact: ###-####.
|
Plumbing Rough-in | 11/8/2000 | 11/9/2000 | 11/9/2000 | A | PASS |
Gary Ziegler
|
|
|
Scheduled by a contractor via Hello! on 11/08/2000 at 15:31:36. Contact: ###-####.
|
Plumbing Rough-in | 11/8/2000 | 11/8/2000 | 11/8/2000 | P | FAIL |
Gary Ziegler
|
|
|
Scheduled by a contractor via Hello! on 11/08/2000 at 11:06:07. Contact: ###-####.
|