Final | 3/13/2002 | 3/14/2002 | 3/14/2002 | A | PASS |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 03/13/2002 at 14:08:04. Contact: ###-####.
|
Final | 2/12/2002 | 2/13/2002 | 2/13/2002 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 02/12/2002 at 10:38:50. Contact: ###-####. set sink in tray wash area, set proofer/steamer in kitchen equipment line, cut roof membrain from roof drain bodies, run water heater t&p drain to service sink 2/13/2002 10:01:36 AM
|
Other | 11/14/2001 | 11/14/2001 | 11/14/2001 | P | PART |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 11/14/2001 3:21:39 PM conference on kitchen equipment hook up
|
Final | 11/5/2001 | 11/6/2001 | 11/6/2001 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 11/05/2001 at 15:38:37. Contact: ###-####. pipe t&p drains and pan drains to approved location, complete air handler make up water piping, test all backflow preventors, temp occ ok 11/6/2001 11:57:23 AM
|
Plumbing Rough-in | 10/23/2001 | 10/24/2001 | 10/24/2001 | A | PASS |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 10/23/2001 at 14:37:54. Contact: ###-####. big dishwasher area oin cafeteria. 10/24/2001 9:22:22 AM
|
Plumbing Rough-in | 9/17/2001 | 9/19/2001 | 9/19/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 09/17/2001 at 08:39:04. Contact: ###-####. iw test drum unload system 9/18/2001 10:50:30 AM
|
Plumbing Rough-in | 9/18/2001 | 9/18/2001 | 9/18/2001 | A | PART |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 9/18/2001 11:11:02 AM kitchen water complete
|
Plumbing Rough-in | 9/6/2001 | 9/6/2001 | 9/6/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 09/06/2001 at 07:44:59. Contact: ###-####.
|
Plumbing Rough-in | 8/29/2001 | 8/29/2001 | 8/29/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 08/29/2001 at 08:20:23. Contact: ###-####. partial water system test in the kitchen 8/29/2001 2:43:03 PM
|
Plumbing Rough-in | 8/14/2001 | 8/15/2001 | 8/15/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 08/14/2001 at 14:30:51. Contact: ###-####. partial ri ok potable water branch mains in kitchen test ok 8/15/2001 2:41:15 PM
|
Water and/or Sewer | 8/6/2001 | 8/7/2001 | 8/7/2001 | A | PART |
Bill VanDegrift
|
|
|
WATER R/I - ###-#### -RM MECH scullery water test ok 8/7/2001 9:38:12 AM
|
Roof Drains | 7/23/2001 | 7/23/2001 | 7/23/2001 | P | PART |
Bill VanDegrift
|
|
|
###-#### 2 -6" rd, 1-8"rd, 1-3" vent from comb. v&v 7/23/2001 3:05:19 PM
|
Roof Drains | 7/20/2001 | 7/20/2001 | 7/20/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 07/20/2001 at 08:53:22. Contact: ###-####. one 8" r.d. n.w. corner kitchen test ok 7/20/2001 2:04:18 PM
|
Plumbing Rough-in | 7/12/2001 | 7/12/2001 | 7/12/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 07/12/2001 at 08:17:09. Contact: ###-####. 4 vents thru roof 2 -2" and 2 -3" kitchen 7/12/2001 3:00:48 PM
|
Plumbing Rough-in | 7/9/2001 | 7/9/2001 | 7/9/2001 | P | PART |
Bill VanDegrift
|
|
|
###-#### waste and vent misc waste and vents in the kitchen 7/9/2001 10:23:07 AM
|
Plumbing Rough-in | 6/21/2001 | 6/22/2001 | 6/22/2001 | P | PASS |
Lee Rice
|
|
|
Scheduled by a contractor via Hello! on 06/21/2001 at 14:01:26. Contact: ###-####.
|
Plumbing Rough-in | 5/10/2001 | 5/10/2001 | 5/10/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 05/10/2001 at 07:44:02. Contact: ###-####. last condensate 5/10/2001 3:49:50 PM
|
Plumbing Rough-in | 5/7/2001 | 5/7/2001 | 5/7/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 05/07/2001 at 10:29:55. Contact: ###-####. potable water north end basement, 1st 1nd 2nd floors 5/7/2001 3:40:24 PM
|
Plumbing Rough-in | 4/30/2001 | 4/30/2001 | 4/30/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 04/30/2001 at 10:03:05. Contact: ###-####. lavs 1st and 2nd floor north resrtoom 4/30/2001 4:07:05 PM
|
Plumbing Rough-in | 4/24/2001 | 4/24/2001 | 4/24/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 04/24/2001 at 08:51:49. Contact: ###-####. north west restroom w&v test 1st and 2nd, rd stub south west test ok 4/24/2001 5:03:21 PM
|
Plumbing Rough-in | 4/23/2001 | 4/23/2001 | 4/23/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 04/23/2001 at 10:28:20. Contact: ###-####. condensate north west end 4/23/2001 4:40:56 PM
|
Roof Drains | 4/19/2001 | 4/19/2001 | 4/19/2001 | P | PART |
Jim Johnson
|
|
|
Scheduled by Inspector: 309 On 4/19/2001 9:15:23 AM ###-####-lane triplet, 4/19/2001 9:18:04 AM roof and overflow drains on east and west canopy ok on building 36 4/19/2001 4:26:14 PM
|
Storm Drains | 4/18/2001 | 4/19/2001 | 4/19/2001 | A | CANC |
Lee Rice
|
|
|
Scheduled by a contractor via Hello! on 04/18/2001 at 15:22:30. Contact: ###-####.
|
Roof Drains | 4/5/2001 | 4/5/2001 | 4/5/2001 | P | PART |
Bill VanDegrift
|
|
|
Les ###-#### rd over basement test ok 4/5/2001 3:12:24 PM
|
Roof Drains | 4/4/2001 | 4/4/2001 | 4/4/2001 | P | PART |
Bill VanDegrift
|
|
|
###-#### 2 rd 3 ofd test ok 4/4/2001 3:43:31 PM
|
Storm Drains | 3/19/2001 | 3/19/2001 | 3/19/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 03/19/2001 at 10:30:43. Contact: . 3 set of rd center and condensat 3/19/2001 3:54:36 PM e center section 3/19/2001 3:54:45 PM
|
Plumbing Rough-in | 3/9/2001 | 3/9/2001 | 3/9/2001 | P | PART |
Jim Johnson
|
|
|
###-#### arear (7) first and second floor men and women rest room and break room sinks water only air test ok. second floor men restroom water needs nail-plates missing a few riser clamps on vents through floor. 3/9/2001 3:12:16 PM
|
Plumbing Rough-in | 2/27/2001 | 2/27/2001 | 2/27/2001 | P | PART |
Jim Johnson
|
|
|
###-#### area 7 first and second floor men and women restrooms waste and vents through roof water test ok. need hangers on horizontal vents in first and second floor plumbing chase 2/27/2001 4:14:53 PM
|
Plumbing Rough-in | 2/16/2001 | 2/16/2001 | 2/16/2001 | P | PART |
Jim Johnson
|
|
|
###-#### area-7 men and women laves waste and vents to second floor plus first floor drinking fountain waste and vent only water test ok 2/16/2001 3:04:49 PM
|