Final | 8/22/2001 | 8/24/2001 | 8/24/2001 | A | PASS |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 08/22/2001 at 14:48:14. Contact: ###-####.double check on hose reel by plants in progress singed occ card 8/24/2001 2:45:36 PM
|
Roof Drains | 8/22/2001 | 8/24/2001 | 8/24/2001 | A | PASS |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 08/22/2001 at 14:47:46. Contact: ###-####.all four roof drainlines tested ok 8/24/2001 2:43:05 PM 8/24/2001 2:44:06 PM
|
Final | 8/17/2001 | 8/20/2001 | 8/20/2001 | A | NR |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 08/17/2001 at 09:19:58. Contact: ###-####.roof drains not tested not ready for final 8/20/2001 2:26:57 PM
|
PLM-Aging Inspection | 8/16/2001 | 8/16/2001 | 8/16/2001 | | CANC |
Lee Rice
|
|
|
|
Plumbing Rough-in | 6/13/2001 | 6/14/2001 | 6/14/2001 | A | PART |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 06/13/2001 at 13:16:31. Contact: ###-####.four frost free hosebibs three in walls one on roof ok 6/14/2001 10:09:55 AM
|
Plumbing Rough-in | 6/5/2001 | 6/6/2001 | 6/6/2001 | A | PART |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 06/05/2001 at 10:19:24. Contact: ###-####.kitchen area Ro system water and waste ok 6/6/2001 10:03:39 PM
|
Plumbing Rough-in | 6/1/2001 | 6/1/2001 | 6/1/2001 | P | PART |
Lee Rice
|
|
|
Scheduled by a contractor via Hello! on 06/01/2001 at 08:25:45. Contact: ###-####.south west breakroom 6/1/2001 2:04:51 PM
|
Plumbing Rough-in | 5/22/2001 | 5/23/2001 | 5/23/2001 | A | PART |
Lee Rice
|
|
|
Scheduled by Inspector: 309 On 5/22/2001 11:05:14 PM te 5/23/2001 12:04:39 PM test passed, but still need to support 2 inch vert vents and bolt chair carrier to floor. 5/23/2001 12:05:54 PM
|
Plumbing Rough-in | 5/21/2001 | 5/22/2001 | 5/22/2001 | P | PART |
Lee Rice
|
|
|
Scheduled by a contractor via Hello! on 05/21/2001 at 15:38:16. Contact: ###-####. Mens and womens restrooms...northside ok, lee will ck back in a.m. on one carrier joint 5/22/2001 4:39:04 PM
|
Plumbing Rough-in | 5/21/2001 | 5/21/2001 | 5/21/2001 | P | PART |
Lee Rice
|
|
|
Scheduled by a contractor via Hello! on 05/21/2001 at 10:37:35. Contact: ###-####.east side bathroom 5/21/2001 2:23:27 PM
|
Groundwork | 4/3/2001 | 4/3/2001 | 4/3/2001 | P | PART |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 04/03/2001 at 08:27:48. Contact: ###-####.main line and mop sink s/w corner 4/3/2001 3:09:38 PM
|
Groundwork | 4/2/2001 | 4/2/2001 | 4/2/2001 | P | PART |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 04/02/2001 at 08:31:35. Contact: ###-####.top ground work west side kitchen deli grease drains 4/2/2001 11:54:20 AM bathrooms on north side 4/2/2001 12:11:02 PM
|
Roof Drains | 3/30/2001 | 3/30/2001 | 3/30/2001 | P | PART |
Stan Johnson
|
|
|
grease traps terri ###-#### grease lines ri complete to intersepter 3/30/2001 12:30:05 PM
|
Groundwork | 3/28/2001 | 3/29/2001 | 3/29/2001 | P | PART |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 03/28/2001 at 16:23:24. Contact: ###-####.
|
Roof Drains | 3/28/2001 | 3/28/2001 | 3/28/2001 | P | PART |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 03/28/2001 at 10:34:49. Contact: ###-####.under ground 4 roof drains ok to cover will test in side buildingwith vertical piping 3/28/2001 11:13:41 AM
|
Water and/or Sewer | 3/22/2001 | 3/23/2001 | 3/23/2001 | P | PART |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 03/22/2001 at 14:17:30. Contact: ###-####.water stub in ok sewer c/o stub ins o/k will test with ground work 3/23/2001 2:39:44 PM
|