Final | 4/13/2001 | 4/13/2001 | 4/13/2001 | P | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 04/13/2001 at 09:42:22. Contact: ###-####.
|
Groundwork | 3/20/2001 | 3/20/2001 | 3/20/2001 | P | FAIL |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 03/20/2001 at 08:26:21. Contact: ###-####.this is a plumbing rough-in toilet and tub vent needs to be 6-inches above flood level rim of fixture before offsetting horizontally 3/20/2001 2:22:42 PM
|
Plumbing Rough-in | 3/20/2001 | 3/20/2001 | 3/20/2001 | P | PASS |
Jim Johnson
|
|
|
Scheduled by Inspector: 360 On 3/20/2001 3:08:59 PM
|