Final | 7/23/2001 | 7/23/2001 | 7/23/2001 | P | PASS |
Jim Johnson
|
|
|
###-####
|
Final | 6/13/2001 | 6/14/2001 | 6/14/2001 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 06/13/2001 at 14:31:07. Contact: ###-####. partial final for womans handicap addition laves in women still need to be sealed 6/14/2001 10:19:06 AM
|
Final | 6/12/2001 | 6/12/2001 | 6/12/2001 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 06/12/2001 at 11:14:34. Contact: ###-####. deli is where the final is partial final temp. on deli ok need to finish condensation drain and to provide grates for floor sink's 6/12/2001 3:28:27 PM
|
Final | 5/18/2001 | 5/21/2001 | 5/21/2001 | A | PART |
Gerry Varner
|
|
|
Scheduled by a contractor via Hello! on 05/18/2001 at 13:46:25. Contact: ###-####. partial final bathroom on west side
|
Plumbing Rough-in | 5/11/2001 | 5/14/2001 | 5/14/2001 | A | PASS |
Gerry Varner
|
|
|
Scheduled by a contractor via Hello! on 05/11/2001 at 13:37:28. Contact: ###-####. deli area
|
Groundwork | 5/7/2001 | 5/8/2001 | 5/8/2001 | A | PASS |
Gerry Varner
|
|
|
Scheduled by a contractor via Hello! on 05/07/2001 at 14:47:10. Contact: ###-####. in the deli area
|
Plumbing Rough-in | 5/2/2001 | 5/3/2001 | 5/3/2001 | A | PART |
Gerry Varner
|
|
|
Scheduled by a contractor via Hello! on 05/02/2001 at 14:50:23. Contact: ###-####.
|
Groundwork | 4/25/2001 | 4/25/2001 | 4/25/2001 | P | PASS |
Gerry Varner
|
|
|
Scheduled by a contractor via Hello! on 04/25/2001 at 09:52:11. Contact: ###-####.
|