Permit Information
Permit NumberPLM01-02513
StatusFinaled
Name CLOVERDALE PLUMBING CO
Site Address 190 E BANNOCK ST
Project NameST LUKES-EAST TOWER
Customer Number439
ePlanReview 
Description
7/27/01-Plumbing system/medical gas piping-$313,947.00-Initial cert. of value.mps 11/21 final cert 438,104.00
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final3/6/20023/6/20023/6/2002APASS
DetailsGary Ziegler
Scheduled by Inspector: 334 On 3/6/2002 8:57:55 AM
Final3/5/20023/5/20023/5/2002APART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 3/5/2002 8:49:38 AM
Final3/1/20023/1/20023/1/2002APART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 3/1/2002 8:27:11 AM
Med/Gas Systems2/22/20022/22/20022/22/2002PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 2/22/2002 12:56:20 PM
Med/Gas Systems2/20/20022/20/20022/20/2002APASS
DetailsGary Ziegler
Scheduled by Inspector: 334 On 2/20/2002 11:31:58 AM
Med/Gas Systems2/19/20022/19/20022/19/2002PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 2/19/2002 10:29:12 AM
Final2/11/20022/11/20022/11/2002ANR
DetailsGary Ziegler
Scheduled by Inspector: 334 On 2/11/2002 10:30:11 AM
Final2/11/20022/11/20022/11/2002PCANC
DetailsGary Ziegler
Scheduled by Inspector: 334 On 2/11/2002 12:39:06 PM
Final2/11/20022/11/20022/11/2002PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 2/11/2002 12:39:06 PM
Med/Gas Systems2/4/20022/5/20022/5/2002PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 2/4/2002 12:25:03 PM
Med/Gas Systems2/4/20022/4/20022/4/2002PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 2/4/2002 11:39:43 AM
Med/Gas Systems1/30/20021/30/20021/30/2002ANR
DetailsGary Ziegler
Scheduled by Inspector: 334 On 1/30/2002 8:40:45 AM
Med/Gas Systems1/30/20021/30/20021/30/2002PNR
DetailsGary Ziegler
Scheduled by Inspector: 334 On 1/30/2002 10:04:12 AM
Plumbing Rough-in1/23/20021/23/20021/23/2002PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 1/23/2002 9:26:19 AM
Final1/17/20021/18/20021/18/2002APART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 1/17/2002 3:31:09 PM first floor er only gz 1/18/2002 3:04:51 PM
Med/Gas Systems1/17/20021/18/20021/18/2002APART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 1/17/2002 3:32:02 PM
Final1/11/20021/11/20021/11/2002PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 1/11/2002 12:28:05 PM
Med/Gas Systems1/3/20021/3/20021/3/2002PCANC
DetailsGary Ziegler
Added by Inspector: 334 On 1/3/2002 12:53:18 PM
Med/Gas Systems1/3/20021/3/20021/3/2002PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 1/3/2002 12:56:18 PM
Med/Gas Systems1/3/20021/3/20021/3/2002PPASS
DetailsGary Ziegler
Scheduled by Inspector: 334 On 1/3/2002 1:40:10 PM
Med/Gas Systems12/28/200112/28/200112/28/2001PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 12/28/2001 8:52:34 AM 150 psi test sub basement 12/28/2001 2:40:14 PM
Med/Gas Systems12/21/200112/21/200112/21/2001PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 12/21/2001 9:40:16 AM
Med/Gas Systems12/19/200112/19/200112/19/2001PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 12/19/2001 8:50:06 AM
Med/Gas Systems12/18/200112/18/200112/18/2001PPASS
DetailsGary Ziegler
Scheduled by Inspector: 334 On 12/18/2001 1:46:34 PM
Med/Gas Systems12/11/200112/11/200112/11/2001PPASS
DetailsGary Ziegler
Scheduled by Inspector: 334 On 12/11/2001 11:24:10 AM
Plumbing Rough-in12/11/200112/11/200112/11/2001APASS
DetailsGary Ziegler
Scheduled by Inspector: 334 On 12/11/2001 11:25:10 AM
Med/Gas Systems12/11/200112/10/200112/10/2001PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 12/11/2001 11:23:20 AM
Plumbing Rough-in11/23/200111/23/200111/23/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 11/23/2001 at 08:57:31. Contact: ###-####.
Plumbing Rough-in11/23/200111/23/200111/23/2001PPASS
DetailsGary Ziegler
Scheduled by Inspector: 334 On 11/23/2001 1:32:18 PM
Plumbing Rough-in11/23/200111/23/200111/23/2001PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 11/23/2001 1:34:32 PM
Plumbing Rough-in11/19/200111/20/200111/20/2001APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 11/19/2001 at 15:41:12. Contact: ###-####.
Med/Gas Systems10/25/200110/25/200110/25/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 10/25/2001 at 11:00:07. Contact: ###-####.
Plumbing Rough-in10/25/200110/25/200110/25/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 10/25/2001 at 10:59:25. Contact: ###-####.
Med/Gas Systems10/24/200110/24/200110/24/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 10/24/2001 at 09:03:21. Contact: ###-####.
Plumbing Rough-in10/24/200110/24/200110/24/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 10/24/2001 at 09:02:38. Contact: ###-####.
Plumbing Rough-in10/16/200110/17/200110/17/2001APART
DetailsLee Rice
Scheduled by a contractor via Hello! on 10/16/2001 at 16:16:25. Contact: ###-####.
Plumbing Rough-in10/17/200110/17/200110/17/2001PPART
DetailsLee Rice
Scheduled by Inspector: 309 On 10/17/2001 10:58:36 AM
Plumbing Rough-in10/17/200110/17/200110/17/2001PPART
DetailsLee Rice
Scheduled by Inspector: 309 On 10/17/2001 11:05:50 AM witnessesed 2 tests and did inspections on waste piping on 2nd floor north side NICU. 10/17/2001 3:11:51 PM
Plumbing Rough-in10/11/200110/12/200110/12/2001APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 10/11/2001 at 13:50:46. Contact: ###-####.
Plumbing Rough-in10/11/200110/11/200110/11/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 10/11/2001 at 08:37:46. Contact: ###-####.
Plumbing Rough-in10/9/200110/10/200110/10/2001APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 10/09/2001 at 16:42:08. Contact: ###-####.
Plumbing Rough-in10/10/200110/10/200110/10/2001PCANC
DetailsGary Ziegler
Added by Inspector: 334 On 10/10/2001 11:10:34 AM
Plumbing Rough-in10/10/200110/10/200110/10/2001PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 10/10/2001 11:11:28 AM
Med/Gas Systems10/8/200110/8/200110/8/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 10/08/2001 at 10:14:18. Contact: ###-####.
Med/Gas Systems10/4/200110/4/200110/4/2001PPART
DetailsJim Johnson
Scheduled by a contractor via Hello! on 10/04/2001 at 11:05:10. Contact: ###-####. second floor area D 10/4/2001 4:19:59 PM
Plumbing Rough-in10/4/200110/4/200110/4/2001PPART
DetailsJim Johnson
Scheduled by a contractor via Hello! on 10/04/2001 at 11:04:26. Contact: ###-####.second floor area A and D 10/4/2001 4:21:07 PM
Plumbing Rough-in9/24/20019/24/20019/24/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 09/24/2001 at 10:46:00. Contact: ###-####.
Med/Gas Systems9/19/20019/19/20019/19/2001PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 9/19/2001 11:36:16 AM
Med/Gas Systems9/17/20019/18/20019/18/2001APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 09/17/2001 at 15:33:54. Contact: ###-####.
Med/Gas Systems9/18/20019/18/20019/18/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 09/18/2001 at 09:48:52. Contact: ###-####.
Plumbing Rough-in9/13/20019/13/20019/13/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 09/13/2001 at 11:08:49. Contact: ###-####.
Plumbing Rough-in9/12/20019/12/20019/12/2001PPASS
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 09/12/2001 at 09:29:47. Contact: ###-####.
Med/Gas Systems9/6/20019/6/20019/6/2001PPASS
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 09/06/2001 at 11:19:11. Contact: ###-####.
Med/Gas Systems9/5/20019/5/20019/5/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 09/05/2001 at 11:05:49. Contact: ###-####.
Med/Gas Systems8/23/20018/24/20018/24/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 08/23/2001 at 14:21:37. Contact: ###-####.
Med/Gas Systems8/23/20018/23/20018/23/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 08/23/2001 at 08:39:59. Contact: ###-####.
Water and/or Sewer8/23/20018/23/20018/23/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 08/23/2001 at 08:40:41. Contact: ###-####.
Med/Gas Systems8/21/20018/22/20018/22/2001APART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 8/21/2001 11:45:02 AM
Med/Gas Systems8/21/20018/21/20018/21/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 08/21/2001 at 11:17:28. Contact: .
Plumbing Rough-in8/21/20018/21/20018/21/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 08/21/2001 at 08:33:24. Contact: .
Med/Gas Systems8/16/20018/17/20018/17/2001ANR
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 08/16/2001 at 15:40:18. Contact: ###-####.
Plumbing Rough-in8/17/20018/17/20018/17/2001PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 8/17/2001 10:22:48 AM
Plumbing Rough-in8/16/20018/17/20018/17/2001APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 08/16/2001 at 15:39:40. Contact: ###-####.
Med/Gas Systems8/16/20018/16/20018/16/2001PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 8/16/2001 9:50:59 AM
Plumbing Rough-in8/16/20018/16/20018/16/2001PPART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 8/16/2001 9:53:19 AM
Med/Gas Systems8/14/20018/15/20018/15/2001APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 08/14/2001 at 11:46:57. Contact: ###-####. 150 psi test 8/15/2001 12:09:44 PM
Plumbing Rough-in8/14/20018/15/20018/15/2001APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 08/14/2001 at 11:46:16. Contact: ###-####.
Plumbing Rough-in8/7/20018/7/20018/7/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 08/07/2001 at 09:53:40. Contact: ###-####.
Plumbing Rough-in8/6/20018/6/20018/6/2001PNR
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 08/06/2001 at 10:15:13. Contact: ###-####.
Plumbing Rough-in8/2/20018/2/20018/2/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 08/02/2001 at 09:54:57. Contact: ###-####.
Plumbing Rough-in8/1/20018/1/20018/1/2001PPASS
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 08/01/2001 at 08:49:34. Contact: ###-####.
Med/Gas Systems7/30/20017/31/20017/31/2001APART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 7/30/2001 4:09:33 PM
Plumbing Rough-in7/30/20017/31/20017/31/2001APART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 7/30/2001 4:10:19 PM
Med/Gas Systems7/27/20017/30/20017/30/2001APART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 07/27/2001 at 12:02:55. Contact: ###-####.
Med/Gas Systems7/30/20017/30/20017/30/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 07/30/2001 at 11:03:00. Contact: ###-####.
Med/Gas Systems7/30/20017/30/20017/30/2001APART
DetailsGary Ziegler
Scheduled by Inspector: 334 On 7/30/2001 4:06:53 PM
Plumbing Rough-in7/30/20017/30/20017/30/2001PPART
DetailsGary Ziegler
Scheduled by a contractor via Hello! on 07/30/2001 at 11:02:14. Contact: ###-####.