Final | 9/17/2001 | 9/17/2001 | 9/17/2001 | A | PASS |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 09/17/2001 at 07:26:21. Contact: ###-####.
|
Plumbing Rough-in | 8/7/2001 | 8/7/2001 | 8/7/2001 | P | PASS |
Stan Johnson
|
|
|
r/i ###-#### re-insp-- john
|
Plumbing Rough-in | 8/6/2001 | 8/6/2001 | 8/6/2001 | P | FAIL |
Stan Johnson
|
|
|
R/I ###-#### -JOHN strap 3/4 to upstairs north and south runns underneath ake strain off 1/2" supplys to 1/2 bath downstairs 90's and risers strap tub supply lines up stairs and down isolate shower supplys masterr bath from fiberglass
8/6/2001 1:20:27 PM
|