Information based on query as of Monday, July 1, 2024.
Permit Information
Permit NumberPLM01-02645
StatusFinaled
Name ALL VALLEY PLUMBING
Site Address 2393 S GEKELER LN
Project NameHOUSE MOVE
Customer Number 
ePlanReview 
Description
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final12/27/200112/28/200112/28/2001APASS
DetailsBill VanDegrift
Scheduled by a contractor via Hello! on 12/27/2001 at 12:49:37. Contact: ###-####. final ok with test caps removed from the vtr's and basement tub and laundry sink wastes capped. basement fixtures are future. 12/28/2001 9:38:19 AM
Plumbing Rough-in10/10/200110/10/200110/10/2001PPASS
DetailsBill VanDegrift
Scheduled by a contractor via Hello! on 10/10/2001 at 10:13:27. Contact: ###-####.
Plumbing Rough-in10/9/200110/9/200110/9/2001PFAIL
DetailsBill VanDegrift
Scheduled by a contractor via Hello! on 10/09/2001 at 09:18:45. Contact: ###-####. nail plate water service piping in basement utility room wall, test failed on kitchen sink and utility room waste and vent systems, garage bathroom floor and walls must be constructed as a shower if it is to be ued as a shower. garage waste and vent test failed. 10/9/2001 4:13:28 PM
Plumbing Rough-in10/5/200110/5/200110/5/2001PCANC
DetailsJim Johnson
Scheduled by a contractor via Hello! on 10/05/2001 at 10:50:11. Contact: ###-####. 10-5-01 JEANEE CALLED IN TO CANC INSPECTION///DLD
Plumbing Rough-in10/5/200110/5/200110/5/2001PCANC
DetailsJim Johnson
Scheduled by a contractor via Hello! on 10/05/2001 at 10:50:11. Contact: ###-####. canc . by plumbing contractor 10/5/2001 2:11:33 PM
Groundwork9/5/20019/5/20019/5/2001PPART
DetailsBill VanDegrift
###-####- jim another groundwork gar 9/5/2001 2:45:18 PM age gw ok 9/5/2001 2:45:25 PM
Groundwork8/6/20018/7/20018/7/2001APASS
DetailsBill VanDegrift
###-#### early am want to pour