Final | 11/20/2001 | 11/20/2001 | 11/20/2001 | P | PASS |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 11/20/2001 at 08:11:04. Contact: ###-####.
|
Final | 11/8/2001 | 11/8/2001 | 11/8/2001 | P | PASS |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 11/08/2001 at 08:58:03. Contact: ###-####.
|
Final | 11/8/2001 | 11/8/2001 | 11/8/2001 | P | FAIL |
Bill VanDegrift
|
|
|
Added by Inspector: 330 On 11/8/2001 4:11:20 PM needs strainers and airgap on t&p drain got the revised plan and will attach to record drawings, the other final here for today was a mistake
|
Final | 10/5/2001 | 10/5/2001 | 10/5/2001 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 10/05/2001 at 07:29:12. Contact: ###-####. need revised plan showing waste piping to interceptor instead of trap. need to install ice machine, caulk sink,s to wall . provide bee hive strainer,s for floor sinkes. oked temp occ. 10/5/2001 1:57:14 PM
|
Plumbing Rough-in | 8/28/2001 | 8/28/2001 | 8/28/2001 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 08/28/2001 at 07:12:56. Contact: ###-####. ok to cover with nail plates, will require a revised plan prior to final showing waste to interceptor instead of trap 8/28/2001 11:07:17 AM
|
Groundwork | 8/27/2001 | 8/27/2001 | 8/27/2001 | P | FAIL |
Lee Rice
|
|
|
Scheduled by a contractor via Hello! on 08/27/2001 at 07:58:55. Contact: ###-####.need 2 3 inch wall cleanouts and one 3inch floor cleanout 8/27/2001 3:10:29 PM
|