Med/Gas Systems | 3/25/2002 | 3/25/2002 | 3/25/2002 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 03/25/2002 at 08:38:12. Contact: ###-####. N.F.P.A. 99-C 4-5.4.1.3 need system verification and final testing report on level-3 compressed air and vacuum system 3/25/2002 4:05:49 PM
|
Final | 3/22/2002 | 3/22/2002 | 3/22/2002 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 03/22/2002 at 08:32:03. Contact: ###-####.finish installation of equipment in basement oked temp 3/22/2002 3:08:08 PM
|
Final | 3/18/2002 | 3/21/2002 | 3/21/2002 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 03/18/2002 at 09:15:36. Contact: ###-####. 3/21/2002 3:59:28 PM tag and identify all back flow devices install protective cover,s under handicapp lav,s finish installation of equipment in basement 3/21/2002 6:01:01 PM
|
Final | 3/13/2002 | 3/15/2002 | 3/13/2002 | P | CANC |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 03/13/2002 at 09:59:59. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 03/13/2002 at 10:51:28.
|
Med/Gas Systems | 1/3/2002 | 1/4/2002 | 1/4/2002 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by Inspector: 330 On 1/3/2002 1:30:19 PM med gas 24hr test med gas pressure test ok 1/4/2002 11:38:45 AM
|
Med/Gas Systems | 1/2/2002 | 1/3/2002 | 1/3/2002 | A | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 01/02/2002 at 11:33:05. Contact: ###-####. med air test is still up but the vacuum system is bown to 5psi. 1/3/2002 9:15:17 AM
|
Med/Gas Systems | 1/3/2002 | 1/3/2002 | 1/3/2002 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by Inspector: 330 On 1/3/2002 9:14:22 AM air and vacuum test started, vac-17psi, air 156psi 1/3/2002 1:29:32 PM
|
Plumbing Rough-in | 12/20/2001 | 12/21/2001 | 12/21/2001 | A | DONE |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 12/20/2001 at 14:57:17. Contact: ###-####. did rough-in inspection on 12/20/01 12/21/2001 9:21:19 AM
|
Plumbing Rough-in | 12/20/2001 | 12/20/2001 | 12/20/2001 | P | PASS |
Jim Johnson
|
|
|
Scheduled by Inspector: 360 On 12/20/2001 3:39:49 PM
|
Water and/or Sewer | 10/24/2001 | 10/24/2001 | 10/24/2001 | P | PART |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 10/24/2001 at 09:44:27. Contact: ###-####. g/w ok 10/24/2001 2:20:20 PM
|
Water and/or Sewer | 10/22/2001 | 10/22/2001 | 10/22/2001 | P | FAIL |
Gerry Varner
|
|
|
Scheduled by a contractor via Hello! on 10/22/2001 at 09:01:23. Contact: ###-####. install back water valve 10/22/2001 2:12:26 PM
|
Water and/or Sewer | 10/18/2001 | 10/19/2001 | 10/19/2001 | A | PART |
Gerry Varner
|
|
|
Scheduled by a contractor via Hello! on 10/18/2001 at 15:11:15. Contact: ###-####. add back water valve 10/19/2001 12:47:24 PM
|