Final | 2/26/2002 | 2/27/2002 | 2/27/2002 | A | PASS |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 02/26/2002 at 14:47:20. Contact: ###-####.
|
Final | 2/21/2002 | 2/22/2002 | 2/22/2002 | A | FAIL |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 02/21/2002 at 17:00:48. Contact: ###-####. airgap t&p drain in basement, traps are to be the same size as the trap arm serving them. 2/22/2002 2:16:39 PM
|
Plumbing Rough-in | 12/5/2001 | 12/6/2001 | 12/6/2001 | A | PASS |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 12/05/2001 at 13:32:19. Contact: ###-####.
|
Groundwork | 10/29/2001 | 10/29/2001 | 10/29/2001 | P | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 10/29/2001 at 09:35:27. Contact: ###-####.
|