Final | 2/13/2002 | 2/14/2002 | 2/14/2002 | A | PASS |
Jim Johnson
|
|
|
Scheduled by Inspector: 360 On 2/13/2002 12:36:18 PM
|
Final | 2/12/2002 | 2/13/2002 | 2/13/2002 | A | PART |
Jim Johnson
|
|
|
DAREN VOICE PAGER ###-#### have R.P. for soap dispenser tested and certified. finish labling med gas zone valves 2/13/2002 12:35:02 PM
|
Med/Gas Systems | 1/21/2002 | 1/22/2002 | 1/22/2002 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 01/21/2002 at 13:40:15. Contact: ###-####. station manifold outlets tested at 50 psi -ok 1/22/2002 11:55:47 AM
|
Med/Gas Systems | 12/28/2001 | 12/31/2001 | 12/31/2001 | A | PASS |
Bill VanDegrift
|
|
|
Scheduled by Inspector: 360 On 12/28/2001 11:41:14 AM end of 24 hour test ok 12/31/2001 8:35:51 AM
|
Med/Gas Systems | 12/27/2001 | 12/28/2001 | 12/28/2001 | A | PART |
Jim Johnson
|
|
|
###-#### ###-#### start of 24 hr test 12/28/2001 11:42:15 AM
|
Med/Gas Systems | 12/13/2001 | 12/14/2001 | 12/14/2001 | A | PART |
Jim Johnson
|
|
|
Scheduled by Inspector: 360 On 12/13/2001 1:14:46 PM 24 hour test ok for ceiling and in wall in nicu area 12/14/2001 12:11:42 PM
|
Med/Gas Systems | 12/12/2001 | 12/13/2001 | 12/13/2001 | A | PART |
Jim Johnson
|
|
|
SHARON ###-#### DIG-PAGER ###-#### start of 24hr. test 12/13/2001 1:13:56 PM
|
Plumbing Rough-in | 12/3/2001 | 12/4/2001 | 12/4/2001 | A | PASS |
Jim Johnson
|
|
|
PAGER # ###-#### DARREN
|
Plumbing Rough-in | 11/30/2001 | 11/30/2001 | 11/30/2001 | P | NR |
Jim Johnson
|
|
|
###-#### SHARON
|
Plumbing Rough-in | 11/27/2001 | 11/27/2001 | 11/27/2001 | P | PART |
Jim Johnson
|
|
|
###-#### half of rough-in -ok 11/27/2001 4:01:02 PM
|
Groundwork | 11/8/2001 | 11/8/2001 | 11/8/2001 | P | PASS |
Jim Johnson
|
|
|
###-#### SHARON
|
Groundwork | 11/5/2001 | 11/5/2001 | 11/5/2001 | P | PART |
Jim Johnson
|
|
|
###-#### sharon
|