PLM-Aging Inspection | 12/11/2002 | 12/11/2002 | 12/11/2002 | | PASS |
Ron Ginner
|
|
|
finaled but not doc finaled 12/11/2002 9:35:16 PM
|
Final | 1/30/2002 | 1/30/2002 | 1/30/2002 | P | PART |
Stan Johnson
|
|
|
Scheduled by Inspector: 352 On 1/30/2002 12:44:20 PM plumbing ok waiting for med gas paper work 1/30/2002 12:45:54 PM
|
Med/Gas Systems | 1/30/2002 | 1/30/2002 | 1/30/2002 | P | FAIL |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 01/30/2002 at 09:12:40. Contact: ###-####.paper work not on sight for med gas 1/30/2002 12:43:28 PM
|
Plumbing Rough-in | 1/30/2002 | 1/30/2002 | 1/30/2002 | P | CANC |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 01/30/2002 at 09:14:25. Contact: ###-####.
|
Med/Gas Systems | 1/8/2002 | 1/8/2002 | 1/8/2002 | A | PASS |
Stan Johnson
|
|
|
Scheduled by Inspector: 352 On 1/8/2002 10:27:25 PM 24 hour test ok air nit, oxy
1/8/2002 10:32:43 PM
|
Med/Gas Systems | 1/7/2002 | 1/7/2002 | 1/7/2002 | P | PART |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 01/07/2002 at 11:22:55. Contact: ###-####.start 24 hr. test 10:30 am 1/7/2002 11:25:48 PM
|
Plumbing Rough-in | 12/28/2001 | 1/2/2002 | 1/2/2002 | A | PASS |
Stan Johnson
|
|
|
Scheduled by a contractor via Hello! on 12/28/2001 at 15:55:03. Contact: ###-####.
|