PLM-Aging Inspection | 12/18/2002 | 12/18/2002 | 12/18/2002 | | PASS |
Jim Johnson
|
|
|
|
Final | 1/8/2002 | 1/9/2002 | 1/9/2002 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 01/08/2002 at 15:16:14. Contact: ###-####. met with Frank cloverdale plumber oked rp. on ice machine and test and certification on premise protection on this inspection at this time 1/9/2002 4:22:07 PM
|
Final | 1/4/2002 | 1/4/2002 | 1/4/2002 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 01/04/2002 at 10:05:07. Contact: ###-####. eight out of fourteen correction,s have been made the following correction,s still need to be addressed (1) premise backflow need,s to be tested and certified (2) outside sprinkler needs t ested and certified or dug up and capped with all valves and stand pipe removed (3) install rp on ice machine (4) install grease interceptor note west boise sewer district letter on 12/4/01. note this inspection does not cover bathroom requirement,s for handicapped standards at this time 1/4/2002 5:17:39 PM 1/4/2002 5:42:22 PM 1/4/2002 5:49:41 PM
|
Other | 1/4/2002 | 1/4/2002 | 1/4/2002 | A | PART |
Jim Johnson
|
|
|
Scheduled by Inspector: 360 On 1/4/2002 5:14:11 PM had conf. with cloverdale plumber on job site. 1/4/2002 5:17:17 PM
|