PLM-Aging Inspection | 1/3/2003 | 1/3/2003 | 1/3/2003 | | PASS |
Jim Johnson
|
|
|
sprinkler finaled by inspector 309 1/3/2003 9:42:15 AM
|
Final | 7/26/2002 | 7/29/2002 | 7/29/2002 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 07/26/2002 at 11:25:33. Contact: ###-####. need to have sprinkler backflow permited tested and certified oked temp. told general contractor . 7/29/2002 2:32:02 PM
|
Final | 7/26/2002 | 7/26/2002 | 7/26/2002 | P | CANC |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 07/26/2002 at 08:41:52. Contact: ###-####. CANC UNTILL MONDAY THE 29TH
|
Plumbing Rough-in | 7/2/2002 | 7/3/2002 | 7/3/2002 | A | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 07/02/2002 at 11:53:54. Contact: ###-####.
|
Plumbing Rough-in | 6/7/2002 | 6/10/2002 | 6/10/2002 | P | PASS |
Jim Johnson
|
|
|
idaho pump and plumbing ###-####
|