Final | 8/21/2002 | 8/21/2002 | 8/21/2002 | P | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 08/21/2002 at 10:43:40. Contact: ###-####.
|
Final | 8/20/2002 | 8/20/2002 | 8/20/2002 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 08/20/2002 at 09:23:37. Contact: ###-####. premius protection need,s to be tested and certified also need to install expansion tank called contractor and left message also told general contractor 8/20/2002 3:31:54 PM
|
Groundwork | 6/11/2002 | 6/12/2002 | 6/12/2002 | A | PASS |
Jim Johnson
|
|
|