Med/Gas Systems | 1/10/2003 | 1/10/2003 | 1/10/2003 | P | PASS |
Jim Johnson
|
|
|
|
Final | 1/8/2003 | 1/9/2003 | 1/9/2003 | A | FAIL |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 01/08/2003 at 11:47:28. Contact: ###-####. static pressure test failed on dental air system from norco test report need to retest and recertify air system called contractor will recall when ready 1/9/2003 4:32:20 PM
|
Med/Gas Systems | 12/4/2002 | 12/4/2002 | 12/4/2002 | P | PART |
Jim Johnson
|
|
|
24 hr pressure test on med gas test ok 12/4/2002 1:14:05 PM
|
Final | 12/2/2002 | 12/3/2002 | 12/3/2002 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 12/02/2002 at 14:56:46. Contact: ###-####. start of 24 hr. pressure test on med gas 12/3/2002 2:15:32 PM
|
Final | 11/22/2002 | 11/25/2002 | 11/25/2002 | A | CANC |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 11/22/2002 at 13:57:38. Contact: ###-####. canc. by carl not ready 11/25/2002 12:32:27 PM
|
Plumbing Rough-in | 11/21/2002 | 11/21/2002 | 11/21/2002 | P | FAIL |
Jim Johnson
|
|
|
###-#### need to perform general testing on gas and vacuum systems as per NFPA 99C 1999 edition 4-5.4.1.1, 4-5.4.2.1 and 4-5.4.3 11/21/2002 4:26:08 PM
|
Plumbing Rough-in | 11/15/2002 | 11/15/2002 | 11/15/2002 | P | FAIL |
Jim Johnson
|
|
|
###-#### medical gas piping test failed on med gas and vacuum air line piping to be ASTM B 819 specification,s with brazed joints 11/15/2002 5:39:40 PM
|