Final | 12/27/2004 | 12/27/2004 | 12/27/2004 | P | PASS |
Jim Johnson
|
|
|
rob; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
Final | 12/22/2004 | 12/23/2004 | 12/23/2004 | P | PART |
Jim Johnson
|
|
|
rob; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles need to provide non potable signage on all outlet,s down stream of rp in shop area contractor to recall when ready 12/23/2004 2:38:40 PM
|
Final | 11/29/2004 | 11/29/2004 | 11/29/2004 | P | PART |
Jim Johnson
|
|
|
Rob; Phone #: ###-#### Internet Inspection Request from: Jan Rice no occupancy card on job site called contractor left message 11/29/2004 4:16:39 PM
|
Final | 11/22/2004 | 11/23/2004 | 11/23/2004 | A | PART |
Jim Johnson
|
|
|
Rod; Phone #: ###-#### Internet Inspection Request from: Jan Rice need expansion tank installed change water closet seat,s to open frount cap off all future fixture out let drains contractor to recall when ready 11/23/2004 2:38:15 PM
|
PLM-Aging Inspection | 11/3/2004 | 11/3/2004 | 11/3/2004 | | PASS |
Jim Johnson
|
|
|
|
PLM-Aging Inspection | 8/31/2004 | 8/31/2004 | 8/31/2004 | | PASS |
Jim Johnson
|
|
|
still working on project 9/2/2004 12:34:26 PM
|
PLM-Aging Inspection | 6/30/2004 | 6/30/2004 | 6/30/2004 | | PASS |
Jim Johnson
|
|
|
|
Plumbing Rough-in | 4/28/2004 | 4/30/2004 | 4/30/2004 | A | PASS |
Jim Johnson
|
|
|
recheck rough-in ok 4/30/2004 10:13:12 AM
|
PLM-Aging Inspection | 3/15/2004 | 3/15/2004 | 3/15/2004 | | PASS |
Jim Johnson
|
|
|
talked to contractor project on hold 3/22/2004 8:01:02 AM
|
PLM-Aging Inspection | 1/12/2004 | 1/12/2004 | 1/12/2004 | | PASS |
Jim Johnson
|
|
|
called contractor job on hold 1/12/2004 8:49:18 AM
|
PLM-Aging Inspection | 11/11/2003 | 11/11/2003 | 11/11/2003 | | PASS |
Jim Johnson
|
|
|
project still under construction 11/17/2003 2:24:49 PM
|
PLM-Aging Inspection | 9/10/2003 | 9/10/2003 | 9/10/2003 | | PASS |
Jim Johnson
|
|
|
still working on project 9/10/2003 10:28:57 AM
|
Plumbing Rough-in | 7/10/2003 | 7/10/2003 | 7/10/2003 | P | PASS |
Jim Johnson
|
|
|
office area rough-in only 7/10/2003 2:59:03 PM
|
Plumbing Rough-in | 7/9/2003 | 7/9/2003 | 7/9/2003 | P | PART |
Jim Johnson
|
|
|
ROB-- ###-#### air test on drains failed need to retest water system test ok called contractor will recall when ready 7/10/2003 9:33:59 AM
|
Plumbing Rough-in | 7/1/2003 | 7/2/2003 | 7/2/2003 | A | NR |
Jim Johnson
|
|
|
###-#### rob not ready contractor to recall when ready 7/2/2003 3:19:20 PM
|
PLM-Aging Inspection | 6/30/2003 | 6/30/2003 | 6/30/2003 | | PASS |
Jim Johnson
|
|
|
stil working on project 6/30/2003 9:19:27 AM
|
PLM-Aging Inspection | 4/28/2003 | 4/28/2003 | 4/28/2003 | | PASS |
Jim Johnson
|
|
|
|
PLM-Aging Inspection | 2/25/2003 | 2/25/2003 | 2/25/2003 | | PASS |
Jim Johnson
|
|
|
work appears to be continuing 2/25/2003 10:22:57 AM
|
Groundwork | 12/6/2002 | 12/9/2002 | 12/9/2002 | A | PASS |
Jim Johnson
|
|
|
###-#### ground-work in office area ok ok to cover note shop area may require interceptor as per upc 1017.1 12/9/2002 1:23:49 PM
|
Groundwork | 12/6/2002 | 12/9/2002 | 12/9/2002 | A | PASS |
Jim Johnson
|
|
|
###-#### ground-work in office area ok ok to cover note shop area may require interceptor as per upc 1017.1 told general contractor and plumbing contractor to verify before pouring concret in shop area 12/9/2002 1:31:24 PM
|
Groundwork | 12/5/2002 | 12/6/2002 | 12/6/2002 | A | PART |
Jim Johnson
|
|
|
###-#### test on D.W.V. test ok need to change 1 inch supply line to 1 1/4 on water service contractor to recall when ready 12/6/2002 6:41:22 PM
|