Final | 1/16/2004 | 1/16/2004 | 1/16/2004 | P | PASS |
Jim Johnson
|
|
|
###-#### DEAN
|
PLM-Aging Inspection | 1/12/2004 | 1/12/2004 | 1/12/2004 | | PASS |
Jim Johnson
|
|
|
called contractor still working on project 1/12/2004 8:56:35 AM
|
PLM-Aging Inspection | 11/12/2003 | 11/12/2003 | 11/12/2003 | | NR |
Ron Ginner
|
|
|
job still in progress 11/12/2003 8:21:45 AM
|
PLM-Aging Inspection | 9/8/2003 | 9/8/2003 | 9/8/2003 | | PASS |
Jim Johnson
|
|
|
called contractor still working on project 9/9/2003 11:22:51 AM
|
PLM-Aging Inspection | 7/9/2003 | 7/9/2003 | 7/9/2003 | | PASS |
Jim Johnson
|
|
|
work still in progress 7/9/2003 9:10:11 AM
|
Plumbing Rough-in | 5/8/2003 | 5/9/2003 | 5/9/2003 | P | PASS |
Jim Johnson
|
|
|
dean; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
PLM-Aging Inspection | 4/8/2003 | 4/8/2003 | 4/8/2003 | | PASS |
Jim Johnson
|
|
|
work still in progress 4/8/2003 8:28:10 AM
|
Groundwork | 2/6/2003 | 2/6/2003 | 2/6/2003 | P | PASS |
Jim Johnson
|
|
|
|
Plumbing Rough-in | 2/6/2003 | 2/6/2003 | 2/6/2003 | P | NR |
Jim Johnson
|
|
|
###-#### not ready 2/6/2003 4:27:38 PM
|
Plumbing Rough-in | 1/14/2003 | 1/14/2003 | 1/14/2003 | P | NR |
Jim Johnson
|
|
|
slab r/i ###-#### Dean not ready 1/14/2003 4:34:43 PM
|