Final | 6/16/2003 | 6/16/2003 | 6/16/2003 | P | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 6/16/2003 at 9:37:00 AM. Contact: ###-####. 6/16/2003 5:01:07 PM
|
Final | 6/11/2003 | 6/11/2003 | 6/11/2003 | P | PART |
Jim Johnson
|
|
|
need to be corrected for final 1- provide a R.P. for make-up water to boiler 2-need to provide access and clearance for existing R.P. need to move out away from wall for maintenance and repair 3- need to provide identification sign,s for hydrant,s on west side of building and in north wash bay as potable water 4- may need to provide a non-potable water source for pressure washer 6/11/2003 4:47:19 PM
|
Final | 6/6/2003 | 6/6/2003 | 6/6/2003 | P | PART |
Jim Johnson
|
|
|
had to reschedule with Bill and Lee for walk through on 6-10-03 oked temp 6/6/2003 12:31:32 PM
|
Final | 5/29/2003 | 5/30/2003 | 5/30/2003 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 5/29/2003 at 1:57:28 PM. Contact: ###-####. additional cross control connection may be required for the make up water for the boiler have schedule a walk through with Bill with united water and Lee Rice for the 2 or 3 of june 5/30/2003 4:40:48 PM
|
Water and/or Sewer | 4/3/2003 | 4/4/2003 | 4/4/2003 | A | PASS |
Jim Johnson
|
|
|
water line only ###-####- patty
|
Groundwork | 3/25/2003 | 3/25/2003 | 3/25/2003 | P | PASS |
Ron Ginner
|
|
|
###-#### OFFICE interceptor piping and vents installed to above ground. 3/25/2003 10:08:02 AM
|
Groundwork | 3/21/2003 | 3/24/2003 | 3/24/2003 | A | PASS |
Ron Ginner
|
|
|
oil interceptor tested to top of lid. small leak from seal of lid to tank. called walt bumgardner and he said it would be okay. each compartment of the tank must be vented with two inch back to bldg where these vents can be combined when above grade. vent from outlet of tank shall be extended by seperately through roof. 3/24/2003 3:35:38 PM
|
Plumbing Rough-in | 3/20/2003 | 3/21/2003 | 3/21/2003 | A | FAIL |
Jim Johnson
|
|
|
grease trap ###-#### 3/21/2003 10:30:19 AM need to correct inlet and outlet elevation on interceptor and retest tank 3/21/2003 10:47:16 AM
|
Plumbing Rough-in | 3/19/2003 | 3/20/2003 | 3/20/2003 | P | PASS |
Jim Johnson
|
|
|
###-#### underground inspection
|
Water and/or Sewer | 3/18/2003 | 3/19/2003 | 3/19/2003 | A | PART |
Jim Johnson
|
|
|
###-#### water line only test ok ok to cover 3/19/2003 12:20:59 PM
|