Permit Information
Permit NumberPLM03-00837
StatusFinaled
Name INTERMOUNTAIN PIPE
Site Address 9213 W FAIRVIEW AVE
Project Name 
Customer Number 
ePlanReview 
Description
INSTALL PLUMBING FIXTURES,OUT SIDE SEWER SERVICE,1500 GAL GREASE/SAND INTERCEPTOR...PER INITIAL CERT OF VALUE $ 5,200.00//final cert 06/30/03
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final5/22/20035/22/20035/22/2003APASS
DetailsJim Johnson
Final5/13/20035/13/20035/13/2003PPART
DetailsJim Johnson
need to extend sampling port up to grade need gas tight lid,s on interceptor water table in interceptor appear,s to be droping will recheck on 5/15/03 5/13/2003 5:57:46 PM
Final5/12/20035/12/20035/12/2003PPART
DetailsJim Johnson
kirk; Phone #: ###-#### Internet Inspection Request from: Annette Moore need to retest interceptor finish vent piping for interceptor oked temp. 5/12/2003 4:51:47 PM
Water and/or Sewer5/5/20035/5/20035/5/2003PPART
DetailsJim Johnson
sewer line down stream of interceptor test ok ok to cover sewer line only interceptor still need to be retested before cover 5/5/2003 4:46:27 PM
Water and/or Sewer4/30/20034/30/20034/30/2003PFAIL
DetailsJim Johnson
kirk undergorund sewer ; Phone #: ###-#### Internet Inspection Request from: Annette Moore need to provide some good bedding material and to correct reverse grade in varies places in sewer line contractor to recall when ready 4/30/2003 12:43:09 PM
Groundwork4/29/20034/29/20034/29/2003PFAIL
DetailsJim Johnson
KIRK AND ALSO INISPECT GREASE INTERSEPTOR; Phone #: ###-#### Internet Inspection Request from: Darla Downs need to fix leak in interceptor water test failed on sewer line need to add cleanout on back side of interceptor and change 90 to a approved directional fitting 4/29/2003 4:47:41 PM
Groundwork4/9/20034/10/20034/10/2003APASS
DetailsJim Johnson
Scheduled by a contractor via Hello! on 4/9/2003 at 11:51:00 PM. Contact: ###-####.
Plumbing Rough-in4/9/20034/10/20034/10/2003APART
DetailsJim Johnson
Scheduled by a contractor via Hello! on 4/9/2003 at 11:51:34 PM. Contact: ###-####. rest room rough-in ok ok to cover 4/10/2003 12:01:43 PM
Water and/or Sewer4/3/20034/3/20034/3/2003PPART
DetailsJim Johnson
###-#### underground inspection need to replace a.b.s piping to pvc going to interceptor need to change interceptor to boise city approved type sand and oil interceptor contractor to recall when ready for ground work inspection 4/4/2003 3:26:46 PM
Plumbing Rough-in4/1/20034/1/20034/1/2003PPART
DetailsJim Johnson
KIRT ( UNDERGROUNG INSIDE SWR ); Phone #: ###-#### Internet Inspection Request from: Darla Downs ground work for new restroom,s ok ok to cover 4/1/2003 3:06:20 PM