Final | 6/10/2004 | 6/10/2004 | 6/10/2004 | P | PASS |
Jim Johnson
|
|
|
Phone #: ###-#### Internet Inspection Request from: Sonja Hankel
|
PLM-Aging Inspection | 4/20/2004 | 4/20/2004 | 4/20/2004 | | PASS |
Jim Johnson
|
|
|
still working on project 4/20/2004 9:57:06 AM
|
Plumbing Rough-in | 2/17/2004 | 2/18/2004 | 2/18/2004 | P | PASS |
Jim Johnson
|
|
|
mechanical room; Phone #: ###-#### Internet Inspection Request from: Sonja Hankel
|
Plumbing Rough-in | 2/3/2004 | 2/5/2004 | 2/5/2004 | A | NR |
Jim Johnson
|
|
|
not ready 2/5/2004 8:38:27 AM
|
Plumbing Rough-in | 2/5/2004 | 2/5/2004 | 2/5/2004 | P | PART |
Jim Johnson
|
|
|
dwv and water for east wing test ok 2/5/2004 2:25:04 PM
|
Water and/or Sewer | 2/3/2004 | 2/3/2004 | 2/3/2004 | P | PART |
Jim Johnson
|
|
|
Later this afternoon. East wing all three floors. Possible waste and vent on plastic of East wing as well; Phone #: ###-#### Internet Inspection Request from: Sonja Hankel water test ok half of east wing dwv test ok 2/3/2004 3:23:10 PM
|
Plumbing Rough-in | 1/15/2004 | 1/15/2004 | 1/15/2004 | P | PART |
Jim Johnson
|
|
|
The later the better. Water and plastic on the north wing, all three floors. Thank You; Phone #: ###-#### Internet Inspection Request from: Sonja Hankel north wing rough-in test ok 1/15/2004 4:04:53 PM
|
Plumbing Rough-in | 12/17/2003 | 12/17/2003 | 12/17/2003 | P | PART |
Jim Johnson
|
|
|
North-wing 7 units; Phone #: ###-#### Internet Inspection Request from: Sonja Hankel D.W.V. test ok for 7 units 12/17/2003 3:45:43 PM
|
Plumbing Rough-in | 12/16/2003 | 12/16/2003 | 12/16/2003 | P | PART |
Jim Johnson
|
|
|
Rough in on waste and vents, not water. North wing 1st, 2nd, and 3rd floors. Thank you; Phone #: ###-#### Internet Inspection Request from: Sonja Hankel D.W.V on north wing test ok 12/16/2003 3:45:50 PM
|
PLM-Aging Inspection | 11/17/2003 | 11/17/2003 | 11/17/2003 | | NR |
Ron Ginner
|
|
|
job still in progress 11/17/2003 8:07:28 AM
|
Other | 9/3/2003 | 9/4/2003 | 9/4/2003 | A | PASS |
Jim Johnson
|
|
|
Underground inspection; Phone #: ###-#### Internet Inspection Request from: Liz Sasser
|
Groundwork | 9/2/2003 | 9/2/2003 | 9/2/2003 | P | PART |
Jim Johnson
|
|
|
inspection am if possible
Thank you; Phone #: ###-#### Internet Inspection Request from: Liz Sasser groundwork on west side of building ok ok to cover 9/2/2003 3:10:40 PM
|