Information based on query as of Tuesday, July 2, 2024.
Permit Information
Permit NumberPLM03-02411
StatusFinaled
Name LACY MECHANICAL INC
Site Address 7805 W GRATZ DR
Project NameLyle Pearson
Customer Number26-21
ePlanReview 
Description
Plumbing for toilets, lavs, trench drains, water and sewer for new building. per initial cert of value $81,989.00//final cert
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final2/2/20042/3/20042/3/2004APASS
DetailsJim Johnson
Final1/31/20042/2/20042/2/2004APART
DetailsJim Johnson
Scheduled by a contractor via Hello! on 1/31/2004 at 10:24:54 AM. Contact: ###-####.need to finish labling non potable water system and raise spill-proof pressure vacuum breaker up higher by mop sink oked temp 2/2/2004 11:50:14 AM
Plumbing Rough-in12/5/200312/8/200312/8/2003ACANC
DetailsJim Johnson
Scheduled by a contractor via Hello! on 12/5/2003 at 2:52:09 PM. Contact: ###-####. canc by contractor 12/8/2003 9:48:47 AM
Plumbing Rough-in12/8/200312/8/200312/8/2003PPASS
DetailsJim Johnson
Scheduled by a contractor via Hello! on 12/8/2003 at 8:07:41 AM. Contact: ###-####.
Plumbing Rough-in12/1/200312/1/200312/1/2003PPART
DetailsJim Johnson
Scheduled by a contractor via Hello! on 12/1/2003 at 7:36:50 AM. Contact: ###-####.
Roof Drains12/1/200312/1/200312/1/2003PPASS
DetailsJim Johnson
Scheduled by a contractor via Hello! on 12/1/2003 at 7:37:40 AM. Contact: ###-####.
Plumbing Rough-in10/3/200310/6/200310/6/2003APASS
DetailsRon Ginner
Scheduled by a contractor via Hello! on 10/3/2003 at 10:03:54 AM. Contact: ###-####.
Water and/or Sewer9/30/200310/1/200310/1/2003APASS
DetailsJim Johnson
Scheduled by a contractor via Hello! on 9/30/2003 at 1:13:49 PM. Contact: ###-####. sewer line from building to interceptor test ok ok to cover 10/1/2003 11:28:59 AM
Groundwork8/13/20038/14/20038/14/2003APART
DetailsRon Ginner
Scheduled by a contractor via Hello! on 8/13/2003 at 2:10:33 PM. Contact: ###-####. sanitary only. sleeve on water line requested by jim johnson. 8/14/2003 10:48:21 AM
Water and/or Sewer8/8/20038/8/20038/8/2003PPASS
DetailsJim Johnson
Scheduled by a contractor via Hello! on 8/8/2003 at 10:45:52 AM. Contact: ###-####.
Water and/or Sewer8/5/20038/6/20038/6/2003APART
DetailsJim Johnson
###-#### ken sewer line test ok ok to cover still need to water test interceptor contractor to recall when ready 8/6/2003 1:29:00 PM