Final | 6/30/2004 | 7/1/2004 | 7/1/2004 | A | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 6/30/2004 at 4:53:24 PM. Contact: ###-####.
|
PLM-Aging Inspection | 6/30/2004 | 6/30/2004 | 6/30/2004 | | PASS |
Jim Johnson
|
|
|
called contractor will be calling for final soon 6/30/2004 9:12:44 AM
|
Final | 4/29/2004 | 4/30/2004 | 4/30/2004 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 4/29/2004 at 12:36:38 PM. Contact: ###-####. need to install two sinks when cabnet,s are installed oked temp 4/30/2004 9:51:48 AM
|
Plumbing Rough-in | 3/5/2004 | 3/8/2004 | 3/8/2004 | A | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 3/5/2004 at 3:55:21 PM. Contact: ###-####.
|
Groundwork | 1/22/2004 | 1/23/2004 | 1/23/2004 | A | PASS |
Jim Johnson
|
|
|
aaron ###-#### cell
|
Plumbing Rough-in | 1/22/2004 | 1/23/2004 | 1/23/2004 | A | NR |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 1/22/2004 at 11:08:46 AM. Contact: ###-####. not ready 1/23/2004 9:59:27 AM
|