Permit NumberPLM04-00679
StatusFinaled
Name KEITH ROWLEY EXCAVATION INC
Site Address 6851 W TARGEE ST
Project NameGillwood Warehouse #1
Customer Number 
ePlanReview 
Description
Install water & sewer lines per initial cert of value $1500///3/25/04 BAM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
PLM-Aging Inspection3/30/20053/30/20053/30/2005 PASS
DetailsJim Johnson
PLM-Aging Inspection6/4/20046/4/20046/4/2004 PASS
DetailsJim Johnson
still working on project 6/4/2004 9:23:53 AM
Water and/or Sewer3/25/20043/26/20043/26/2004APART
DetailsLee Rice
oked water connections. Left message with contractor to not backfill within 5 feet of interceptor until automatic valve is installed to allow storm water to go to storm drainage. Took Walt B. with me to site for visual and he will call owner and remind him of his plan and commitments to the washdown/interceptor/storm/sewer system and pad.acording to approved plans. 3/26/2004 1:03:59 PM 3/26/2004 1:05:12 PM
Water and/or Sewer3/25/20043/25/20043/25/2004PFAIL
DetailsLee Rice
###-#### gary covered up water connection and no approved plumbing plans on site to verify correct interceptor is installed. Gave approval for partial backfilling middle sections of sewer and water line. 3/25/2004 12:45:16 PM