Final | 7/7/2005 | 7/8/2005 | 7/8/2005 | P | PART |
Jim Johnson
|
|
|
per gary, by lisa; Phone #: ###-#### Internet Inspection Request from: Sonja Hankel
|
PLM-Aging Inspection | 5/30/2005 | 5/30/2005 | 5/31/2005 | | PASS |
Jim Johnson
|
|
|
|
Med/Gas Systems | 3/28/2005 | 3/29/2005 | 3/29/2005 | A | CANC |
Jim Johnson
|
|
|
per Gary, by Lisa; Phone #: ###-#### Internet Inspection Request from: Sonja Hankel canc by gary no med gas system in building 3/29/2005 11:10:31 AM
|
Groundwork | 12/10/2004 | 12/10/2004 | 12/10/2004 | P | PASS |
Jim Johnson
|
|
|
Phone #: ###-#### Internet Inspection Request from: Sonja Hankel
|
Plumbing Rough-in | 11/10/2004 | 11/12/2004 | 11/12/2004 | A | PART |
Jim Johnson
|
|
|
Phone #: ###-#### Internet Inspection Request from: Linda Hartwell first floor restroom rough-in test ok ok to cover 11/12/2004 10:48:10 AM
|
Roof Drains | 10/26/2004 | 10/27/2004 | 10/27/2004 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 10/26/2004 at 4:32:00 PM. Contact: ###-####. roof and overflow drain,s and second floor rough-in test ok 10/27/2004 1:27:25 PM
|
Plumbing Rough-in | 10/25/2004 | 10/26/2004 | 10/26/2004 | A | PART |
Jim Johnson
|
|
|
Phone #: ###-#### Internet Inspection Request from: Sonja Hankel second floor rough-in test ok 10/26/2004 11:24:22 AM
|
Roof Drains | 10/25/2004 | 10/26/2004 | 10/26/2004 | A | PART |
Jim Johnson
|
|
|
please call gary first, he is only have 1/2 of the drains inspected. Thank You; Phone #: ###-#### Internet Inspection Request from: Sonja Hankel roof and overflow on east side of building test ok 10/26/2004 11:25:24 AM
|
Roof Drains | 10/26/2004 | 10/26/2004 | 10/26/2004 | P | PART |
Jim Johnson
|
|
|
this is the other half of the roof drains. please call Gary if any Questions ###-####; Phone #: ###-#### Internet Inspection Request from: Sonja Hankel roof drain,s on west side test ok need to correct leak in overflow drain contractor to recall when ready 10/26/2004 2:46:20 PM
|
Plumbing Rough-in | 10/21/2004 | 10/22/2004 | 10/22/2004 | A | PART |
Jim Johnson
|
|
|
This will be on the 2nd floor; Phone #: ###-#### Internet Inspection Request from: Sonja Hankel need a couple raiser clamp,s and some additional hanger on dwv piping and water lines also need to correct leak on vent above restroom group on second floor and provide nail plates where need water test ok will need ro retset where leak will be corrected on dwv talked to plumber on job site will recall when ready 10/22/2004 11:44:25 AM
|
Groundwork | 10/8/2004 | 10/8/2004 | 10/8/2004 | P | PASS |
Gerry Varner
|
|
|
This willbe ready late this morning you may call Gary if you need to. ###-####; Phone #: ###-#### Internet Inspection Request from: Sonja Hankel
|
Roof Drains | 9/2/2004 | 9/3/2004 | 9/3/2004 | A | PART |
Jim Johnson
|
|
|
Phone #: ###-#### Internet Inspection Request from: Sonja Hankel roof drain on north west corner of building failed air test all other test ok contractor to recall when north west corner drain is ready 9/3/2004 10:48:23 AM
|
Water and/or Sewer | 9/1/2004 | 9/1/2004 | 9/1/2004 | P | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 9/1/2004 at 9:45:18 AM. Contact: ###-####. copper water supply stub from outside building to inside test ok ok to cover 9/1/2004 3:12:14 PM
|
PLM-Aging Inspection | 7/9/2004 | 7/9/2004 | 7/9/2004 | | PASS |
Jim Johnson
|
|
|
still under construction 7/9/2004 8:02:17 AM
|
Groundwork | 5/4/2004 | 5/5/2004 | 5/5/2004 | A | PASS |
Jim Johnson
|
|
|
Phone #: ###-#### Internet Inspection Request from: Sonja Hankel
|