Final | 12/23/2005 | 12/23/2005 | 12/23/2005 | P | PASS |
Daryl Spivey
|
|
|
Scheduled by a contractor via Hello! on 12/23/2005 at 9:00:53 AM. Contact: ###-####.
|
Final | 11/1/2005 | 11/2/2005 | 11/2/2005 | A | PART |
Daryl Spivey
|
|
|
Dale is contact. General contractor, Bruce, would like for you to come into job trailor after inspection to sign off on plans. Thanks.; Phone #: ###-#### Internet Inspection Request from: Mike Davisson Needs temp control on lavs, Shutoff valves at W/H's and strainer in floor sink. ds
|
Plumbing Rough-in | 7/7/2005 | 7/8/2005 | 7/7/2005 | A | CANC |
Daryl Spivey
|
|
|
jason; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
Plumbing Rough-in | 7/7/2005 | 7/7/2005 | 7/7/2005 | P | PASS |
Daryl Spivey
|
|
|
all R/I completed and passed.
|
Roof Drains | 6/7/2005 | 6/7/2005 | 6/7/2005 | P | PASS |
Daryl Spivey
|
|
|
jason; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles roof drains on south end of auditorium
|
Plumbing Rough-in | 5/23/2005 | 5/23/2005 | 5/23/2005 | P | PART |
Daryl Spivey
|
|
|
jayson; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Test on water and waste and vent in main bathroom groups in south end.
|
Roof Drains | 5/19/2005 | 5/19/2005 | 5/19/2005 | P | PASS |
Daryl Spivey
|
|
|
Scheduled by a contractor via Hello! on 5/19/2005 at 7:32:55 AM. Contact: ###-####. auditorium roof drains
|
Roof Drains | 4/12/2005 | 4/13/2005 | 4/13/2005 | P | PART |
Daryl Spivey
|
|
|
Contact person on job site is Jayson.; Phone #: ###-#### Internet Inspection Request from: Michael Davisson Area B done
|
Plumbing Rough-in | 3/16/2005 | 3/21/2005 | 3/21/2005 | A | PART |
Ron Ginner
|
|
|
jason Note: partial plumbing rough in; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles area B water tested and inspected. 3/21/2005 12:23:16 PM
|
Plumbing Rough-in | 2/7/2005 | 2/8/2005 | 2/8/2005 | A | PART |
Ron Ginner
|
|
|
Scheduled by a contractor via Hello! on 2/7/2005 at 1:25:39 PM. Contact: ###-####. roughin on southwest corner-dwv and water for center section with water closets and urninals and lavs to the north of that restroom 2/8/2005 12:34:47 PM
|
Plumbing Rough-in | 11/22/2004 | 11/22/2004 | 11/22/2004 | A | PART |
Ron Ginner
|
|
|
Scheduled by a contractor via Hello! on 11/22/2004 at 7:01:46 AM. Contact: ###-####.
|
Groundwork | 11/9/2004 | 11/10/2004 | 11/10/2004 | A | PASS |
Ron Ginner
|
|
|
Jason; Phone #: ###-#### Internet Inspection Request from: Jan Rice
|
Groundwork | 10/18/2004 | 10/18/2004 | 10/18/2004 | P | PART |
Ron Ginner
|
|
|
Scheduled by a contractor via Hello! on 10/18/2004 at 8:20:20 AM. Contact: ###-####. area B girls bathroom 10/18/2004 3:04:09 PM
|
Groundwork | 10/15/2004 | 10/15/2004 | 10/15/2004 | P | PART |
Ron Ginner
|
|
|
ground work for north end roof drains only
|
Plumbing Rough-in | 10/14/2004 | 10/15/2004 | 10/15/2004 | P | CANC |
Ron Ginner
|
|
|
jason ###-####
|
Groundwork | 10/5/2004 | 10/6/2004 | 10/6/2004 | P | PART |
Ron Ginner
|
|
|
Scheduled by a contractor via Hello! on 10/5/2004 at 4:06:58 PM. Contact: ###-####.
|
Groundwork | 9/7/2004 | 9/8/2004 | 9/8/2004 | A | PART |
Ron Ginner
|
|
|
###-#### - lenny main trunck line okay 9/8/2004 3:40:16 PM
|