Final | 1/25/2006 | 1/26/2006 | 1/26/2006 | A | PASS |
Jim Johnson
|
|
|
Internet Inspection Request from: Brent Lacy
|
Final | 1/23/2006 | 1/23/2006 | 1/24/2006 | P | PART |
Jim Johnson
|
|
|
Will be finished at approximately 10:30 AM. Thank You, Robert Church; Phone #: ###-#### Internet Inspection Request from: Brent Lacy
|
Final | 12/20/2005 | 12/20/2005 | 12/20/2005 | P | PART |
Jim Johnson
|
|
|
late this afternoon.; Phone #: ###-#### Internet Inspection Request from: Brent Lacy pked temp.
|
Final | 12/15/2005 | 12/16/2005 | 12/16/2005 | A | PART |
Jim Johnson
|
|
|
Phone #: ###-#### Internet Inspection Request from: Brent Lacy made walk through with BILL T. from united water and Robert with \Lacy plumbing for backflow location,s
|
PLM-Aging Inspection | 11/1/2005 | 11/1/2005 | 11/1/2005 | | CANC |
Lee Rice
|
|
|
|
Plumbing Rough-in | 8/31/2005 | 9/1/2005 | 9/1/2005 | A | PART |
Jim Johnson
|
|
|
main water trunk line,s in basement test ok
|
Plumbing Rough-in | 8/30/2005 | 8/31/2005 | 8/31/2005 | P | NR |
Jim Johnson
|
|
|
ready after lunch; Phone #: ###-#### Internet Inspection Request from: Brent Lacy
|
Water and/or Sewer | 8/30/2005 | 8/31/2005 | 8/30/2005 | P | CANC |
Jim Johnson
|
|
|
will be ready after lunch; Phone #: ###-#### Internet Inspection Request from: Brent Lacy Inspection cancelled from web by: Brent Lacy
|
Plumbing Rough-in | 8/23/2005 | 8/24/2005 | 8/24/2005 | A | PART |
Jim Johnson
|
|
|
Internet Inspection Request from: Brent Lacy
|
Plumbing Rough-in | 8/4/2005 | 8/5/2005 | 8/5/2005 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 8/4/2005 at 2:08:28 PM. Contact: ###-####. roof canopy drains test ok ok to cover
|
Plumbing Rough-in | 8/4/2005 | 8/5/2005 | 8/4/2005 | A | CANC |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 8/4/2005 at 10:11:44 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Aug 4 2005 2:05PM.
|
PLM-Aging Inspection | 8/3/2005 | 8/3/2005 | 8/3/2005 | | PASS |
Jim Johnson
|
|
|
still working on project
|
Water and/or Sewer | 6/1/2005 | 6/3/2005 | 6/3/2005 | P | CANC |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 6/1/2005 at 9:18:53 AM. Contact: ###-####.
|
Plumbing Rough-in | 6/1/2005 | 6/2/2005 | 6/2/2005 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 6/1/2005 at 5:10:26 PM. Contact: ###-####. basement venting test ok
|
Water and/or Sewer | 6/1/2005 | 6/2/2005 | 6/2/2005 | A | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 6/1/2005 at 5:10:56 PM. Contact: ###-####.
|
Plumbing Rough-in | 5/12/2005 | 5/12/2005 | 5/12/2005 | P | PART |
Jim Johnson
|
|
|
Phone #: ###-#### Internet Inspection Request from: Brent Lacy water complete on first and second floor
|
Plumbing Rough-in | 5/10/2005 | 5/10/2005 | 5/10/2005 | P | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 5/10/2005 at 10:58:35 AM. Contact: ###-####.
|
Plumbing Rough-in | 5/6/2005 | 5/6/2005 | 5/6/2005 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 5/6/2005 at 7:29:32 AM. Contact: ###-####.
|
Plumbing Rough-in | 5/5/2005 | 5/5/2005 | 5/5/2005 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 5/5/2005 at 10:12:27 AM. Contact: ###-####.
|
Plumbing Rough-in | 5/4/2005 | 5/4/2005 | 5/4/2005 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 5/4/2005 at 9:59:41 AM. Contact: ###-####. water lines on 1st and 2nd floor on west side half of building only
|
Plumbing Rough-in | 4/26/2005 | 4/27/2005 | 4/27/2005 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 4/26/2005 at 2:09:40 PM. Contact: ###-####. over head plumbing above pool area on south end test ok 4/27/2005 9:53:00 AM
|
Plumbing Rough-in | 4/14/2005 | 4/15/2005 | 4/15/2005 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 4/14/2005 at 4:31:18 PM. Contact: ###-####. 3rd floor water test ok 4/15/2005 9:36:38 AM
|
Plumbing Rough-in | 4/13/2005 | 4/13/2005 | 4/13/2005 | P | PART |
Jim Johnson
|
|
|
Phone #: ###-#### Internet Inspection Request from: Brent Lacy water system on 3rd floor except room,s over pool area on south end and 3-room,s over lobby area and room 333 test ok 4/13/2005 3:34:20 PM
|
Plumbing Rough-in | 4/5/2005 | 4/5/2005 | 4/5/2005 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 4/5/2005 at 10:21:12 AM. Contact: ###-####. south side of basement dwv only test ok 4/5/2005 2:49:47 PM
|
Plumbing Rough-in | 4/4/2005 | 4/4/2005 | 4/4/2005 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 4/4/2005 at 9:44:29 AM. Contact: ###-####. north side section of basement up to elevator shaft dwv only 4/4/2005 4:10:02 PM
|
Plumbing Rough-in | 4/1/2005 | 4/1/2005 | 4/1/2005 | P | PART |
Jim Johnson
|
|
|
Ready for inspeciton ; Phone #: ###-#### Internet Inspection Request from: Brent Lacy repipe running trap on shower in basement 4/1/2005 4:23:30 PM
|
Plumbing Rough-in | 3/31/2005 | 3/31/2005 | 3/31/2005 | P | PART |
Daryl Spivey
|
|
|
Phone #: ###-#### Internet Inspection Request from: Brent Lacy waste and vent tested on north west end 1st thru 4th floors.
|
Plumbing Rough-in | 3/30/2005 | 3/30/2005 | 3/30/2005 | P | PART |
Jim Johnson
|
|
|
Ready for Inspection.; Phone #: ###-#### Internet Inspection Request from: Brent Lacy 20 room,s on middle of east side test ok 3/30/2005 3:14:05 PM
|
Plumbing Rough-in | 3/28/2005 | 3/29/2005 | 3/29/2005 | A | PART |
Jim Johnson
|
|
|
24 unit,s on south east side test ok on dwv only 3/29/2005 9:25:24 AM
|
Plumbing Rough-in | 3/28/2005 | 3/28/2005 | 3/28/2005 | P | CANC |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 3/28/2005 at 10:20:20 AM. Contact: ###-####. canc by Ken 3/28/2005 3:58:32 PM
|
Plumbing Rough-in | 3/25/2005 | 3/25/2005 | 3/25/2005 | P | PART |
Bill VanDegrift
|
|
|
Phone #: ###-#### Internet Inspection Request from: Brent Lacy west side waste ok 3/25/2005 3:57:54 PM
|
Plumbing Rough-in | 3/23/2005 | 3/24/2005 | 3/24/2005 | A | CANC |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 3/23/2005 at 12:48:58 PM.
|
Plumbing Rough-in | 3/24/2005 | 3/24/2005 | 3/24/2005 | P | PART |
Bill VanDegrift
|
|
|
lobby thru 4th waste and vent 3/24/2005 4:52:22 PM
|
Plumbing Rough-in | 3/24/2005 | 3/24/2005 | 3/24/2005 | P | PART |
Daryl Spivey
|
|
|
test on waste and vent on west end on 1-4 floors. water test on for 4th floor west end.
|
Plumbing Rough-in | 3/22/2005 | 3/22/2005 | 3/22/2005 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 3/22/2005 at 10:24:09 AM. Contact: ###-####. DWV pipiing only on 12 room,s on north end of building test ok 3/22/2005 4:14:51 PM
|
Roof Drains | 3/22/2005 | 3/22/2005 | 3/22/2005 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 3/22/2005 at 10:24:34 AM. Contact: ###-####. roof drain,s and overflow drain on north end and inside building test ok 3/22/2005 4:13:17 PM
|
Roof Drains | 3/11/2005 | 3/11/2005 | 3/11/2005 | P | PART |
Ron Ginner
|
|
|
Phone #: ###-#### Internet Inspection Request from: Brent Lacy west side mainroof drains tested and passed off to cover. 3/11/2005 4:13:20 PM
|
Water and/or Sewer | 3/3/2005 | 3/3/2005 | 3/3/2005 | P | PASS |
Ron Ginner
|
|
|
Scheduled by a contractor via Hello! on 3/3/2005 at 10:35:09 AM. Contact: ###-####. gave correctionnotice for 3034 being installed under a covered driveway. 3/3/2005 1:56:16 PM
|
Water and/or Sewer | 11/1/2004 | 11/2/2004 | 11/2/2004 | A | PASS |
Ron Ginner
|
|
|
Scheduled by a contractor via Hello! on 11/1/2004 at 5:28:43 PM.
|
Water and/or Sewer | 11/1/2004 | 11/1/2004 | 11/1/2004 | P | NR |
Ron Ginner
|
|
|
Scheduled by a contractor via Hello! on 11/1/2004 at 11:19:39 AM. Contact: ###-####. 11/1/2004 2:10:25 PM 11/1/2004 2:12:40 PM
|
Groundwork | 10/21/2004 | 10/21/2004 | 10/21/2004 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 10/21/2004 at 9:35:37 AM. Contact: ###-####. north end first floor ground work test ok ok to cover 10/21/2004 2:42:40 PM
|
Groundwork | 9/30/2004 | 9/30/2004 | 9/30/2004 | P | PART |
Ron Ginner
|
|
|
Scheduled by a contractor via Hello! on 9/30/2004 at 8:52:29 AM. Contact: ###-####. partial grease lines from kit to outside 9/30/2004 1:41:51 PM
|
Groundwork | 9/27/2004 | 9/27/2004 | 9/27/2004 | P | PART |
Jim Johnson
|
|
|
ken; Phone #: ###-#### Internet Inspection Request from: Barbara Moore completion of sanitary sewer on north side of building test ok ok to cover 9/27/2004 11:10:19 AM
|
Groundwork | 9/21/2004 | 9/21/2004 | 9/21/2004 | P | PART |
Ron Ginner
|
|
|
|
Plumbing Rough-in | 9/20/2004 | 9/21/2004 | 9/21/2004 | A | NR |
Jim Johnson
|
|
|
robert- ###-#### not ready 9/21/2004 9:18:00 AM
|