Final | 1/7/2005 | 1/7/2005 | 1/7/2005 | P | PASS |
Ron Ginner
|
|
|
Scheduled by a contractor via Hello! on 1/7/2005 at 8:23:44 AM. Contact: ###-####.
|
Plumbing Rough-in | 10/29/2004 | 10/29/2004 | 10/29/2004 | P | PASS |
Ron Ginner
|
|
|
Scheduled by a contractor via Hello! on 10/29/2004 at 9:10:18 AM. Contact: ###-####.
|
Roof Drains | 10/15/2004 | 10/15/2004 | 10/15/2004 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 10/15/2004 at 9:36:39 AM. Contact: ###-####. roof and overflow drain,s inside building test ov roof drains outside building still need to be tested and inspected 10/15/2004 2:07:10 PM
|
Plumbing Rough-in | 10/1/2004 | 10/4/2004 | 10/4/2004 | A | FAIL |
Jim Johnson
|
|
|
grease line & grease receptor inspection please///###-#### joe interceptor tank leaking on north side need to test drain and vent lines to interceptor also need to use approved materials to make transition from abs to pvc pipe called contractor will recall when ready 10/4/2004 9:32:44 AM
|
Groundwork | 9/22/2004 | 9/22/2004 | 9/22/2004 | P | PASS |
Jim Johnson
|
|
|
joe ###-####
|