Final | 1/19/2005 | 1/19/2005 | 1/19/2005 | P | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 1/19/2005 at 7:41:16 AM. Contact: ###-####.
|
Plumbing Rough-in | 12/17/2004 | 12/17/2004 | 12/17/2004 | P | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 12/17/2004 at 8:11:33 AM. Contact: ###-####.
|
Plumbing Rough-in | 12/16/2004 | 12/16/2004 | 12/16/2004 | P | FAIL |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 12/16/2004 at 7:41:54 AM. Contact: ###-####. test failed on DWV system water test ok 12/16/2004 3:27:04 PM
|
Groundwork | 10/27/2004 | 10/27/2004 | 10/27/2004 | P | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 10/27/2004 at 9:45:45 AM. Contact: ###-####.
|