Final | 3/15/2005 | 3/15/2005 | 3/15/2005 | P | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 3/15/2005 at 7:57:40 AM. Contact: ###-####.
|
Final | 3/11/2005 | 3/11/2005 | 3/11/2005 | P | FAIL |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 3/11/2005 at 9:30:18 AM. Contact: ###-####. need sprinkler permitted , tested , certified and inspected before final plumbing inspection. 2. change cpvc male adapter on t&p valve to approved transition adapter 3 cap off future plumbing in southwest corner of building left correction notice contractor to recall when ready 3/11/2005 2:04:36 PM
|
Plumbing Rough-in | 12/16/2004 | 12/16/2004 | 12/16/2004 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 12/16/2004 at 9:32:41 AM. Contact: ###-####. need to repipe water in overhead in water heater and mop sink area to protect from freezing upc 414.1 limitation of hot water to public laves to 120 degrees will need to make provision for laves 12/16/2004 3:01:31 PM
|
Groundwork | 11/8/2004 | 11/8/2004 | 11/8/2004 | P | PASS |
Jim Johnson
|
|
|
Per Linda, okay for inspection this afternoon
|
Water and/or Sewer | 11/8/2004 | 11/8/2004 | 11/8/2004 | P | DONE |
Jim Johnson
|
|
|
Water & Sewer
|