PLM-Aging Inspection | 7/8/2005 | 7/8/2005 | 7/8/2005 | | PASS |
Jim Johnson
|
|
|
|
DOC - Permit Finaled | 7/8/2005 | 7/8/2005 | 7/8/2005 | P | PASS |
Jim Johnson
|
|
|
|
Final | 5/2/2005 | 5/2/2005 | 5/2/2005 | P | PART |
Jim Johnson
|
|
|
re-insp -- jeff- ###-#### need med gas system verification report for final
|
Final | 4/27/2005 | 4/27/2005 | 4/27/2005 | P | PART |
Jim Johnson
|
|
|
jeff; Phone #: ###-#### Internet Inspection Request from: Barbara Moore oked temp. so equipment can be moved in but no dental work to done until final final med gas certification has been done 4/27/2005 4:37:11 PM
|
Plumbing Rough-in | 4/14/2005 | 4/15/2005 | 4/15/2005 | P | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 4/14/2005 at 1:34:50 PM. Contact: ###-####. lobby area rest room,s test ok 4/15/2005 1:55:54 PM
|
Plumbing Rough-in | 4/12/2005 | 4/13/2005 | 4/13/2005 | A | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 4/12/2005 at 4:01:49 PM. Contact: ###-####. ground work for rest room in lobby area test ok 4/13/2005 10:19:51 AM
|
Other | 4/11/2005 | 4/12/2005 | 4/12/2005 | A | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 4/11/2005 at 12:29:03 PM. Contact: ###-####. vac line test ok 4/12/2005 11:38:28 AM
|
Plumbing Rough-in | 4/7/2005 | 4/8/2005 | 4/8/2005 | P | PASS |
Jim Johnson
|
|
|
pressure test 24 hr test ok on med gas 4/8/2005 4:36:37 PM
|
Plumbing Rough-in | 4/7/2005 | 4/7/2005 | 4/7/2005 | P | PART |
Jim Johnson
|
|
|
###-#### in wall plumbing dwv test ok still need to test water start of 24 hr pressure test on med gas 4/7/2005 4:22:47 PM
|
Groundwork | 3/23/2005 | 3/23/2005 | 3/23/2005 | P | PART |
Bill VanDegrift
|
|
|
partial gw ok needs the restroom, should have the information for it when they get the approved plans.
|
Plumbing Rough-in | 3/23/2005 | 3/23/2005 | 3/23/2005 | P | CANC |
Bill VanDegrift
|
|
|
dave; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|