Final | 8/11/2005 | 8/12/2005 | 8/12/2005 | A | PASS |
Daryl Spivey
|
|
|
Scheduled by a contractor via Hello! on 8/11/2005 at 10:34:35 AM. Contact: ###-####.
|
Plumbing Rough-in | 6/15/2005 | 6/16/2005 | 6/16/2005 | A | PASS |
Jim Johnson
|
|
|
ina; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
Plumbing Rough-in | 6/9/2005 | 6/10/2005 | 6/10/2005 | P | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 6/9/2005 at 9:23:55 AM. Contact: ###-####.need to meet cross-sectional area venting requirement for 4 inch building drain called and talked to plumber will recall when ready
|
Groundwork | 6/7/2005 | 6/7/2005 | 6/7/2005 | P | PASS |
Jim Johnson
|
|
|
|
Plumbing Rough-in | 6/7/2005 | 6/7/2005 | 6/7/2005 | P | NR |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 6/7/2005 at 9:34:44 AM. Contact: ###-####.
|