Final | 1/11/2006 | 1/11/2006 | 1/11/2006 | P | PASS |
Jim Johnson
|
|
|
Jim John was in and said that he turned the paper work into you & Lee regarding the double checks.....could you please call him before you go out??? Thanks John ###-####
|
Final | 12/6/2005 | 12/7/2005 | 12/7/2005 | A | PART |
Jim Johnson
|
|
|
need to install double check,s on hot and cold water to foot bath spa,s contractor to call when ready
|
Final | 12/6/2005 | 12/6/2005 | 12/6/2005 | P | PART |
Jim Johnson
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
Final | 11/17/2005 | 11/18/2005 | 11/18/2005 | A | PART |
Jim Johnson
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles contractor waiting for special order fixture to arrive oked temp
|
Plumbing Rough-in | 11/1/2005 | 11/2/2005 | 11/2/2005 | A | PART |
Bill VanDegrift
|
|
|
John; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa weat end ok
|
Groundwork | 10/7/2005 | 10/7/2005 | 10/7/2005 | P | PASS |
Jim Johnson
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ground work on south side of building ok
|
Plumbing Rough-in | 9/16/2005 | 9/16/2005 | 9/16/2005 | P | PART |
Jim Johnson
|
|
|
trim insp? john; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie need to have existing premius protection tested and certified before final on phase one of project
|
Plumbing Rough-in | 8/11/2005 | 8/11/2005 | 8/11/2005 | P | PART |
Daryl Spivey
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie North end of building R/I ok. Still has south side to do at a later date.Will probably do trim on north side before he starts on south side. ds.
|
Groundwork | 7/8/2005 | 7/8/2005 | 7/8/2005 | P | PASS |
Jim Johnson
|
|
|
john ###-####
|