Final | 10/19/2006 | 10/20/2006 | 10/20/2006 | A | PASS |
Jim Johnson
|
|
|
jeff; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
Final | 10/10/2006 | 10/11/2006 | 10/11/2006 | A | PART |
Eric Strole
|
|
|
JEFF; Phone #: ###-#### Internet Inspection Request from: Darla Downs-need hot water to check for tempered water.
|
Plumbing Rough-in | 8/17/2006 | 8/18/2006 | 8/18/2006 | A | PASS |
Jim Johnson
|
|
|
|
Plumbing Rough-in | 8/16/2006 | 8/17/2006 | 8/17/2006 | A | CANC |
Jim Johnson
|
|
|
jerry - above ground ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley canc by jerry
|
Groundwork | 7/7/2006 | 7/7/2006 | 7/7/2006 | P | PASS |
Jim Johnson
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
Groundwork | 7/6/2006 | 7/6/2006 | 7/6/2006 | P | FAIL |
Jim Johnson
|
|
|
mike ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie test failed on roof strrom drains
|
Groundwork | 7/5/2006 | 7/6/2006 | 7/6/2006 | A | PART |
Jim Johnson
|
|
|
mike ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley need to correct leak on rain drain contractor to recall when ready
|
PLM-Aging Inspection | 7/3/2006 | 7/3/2006 | 7/3/2006 | | PASS |
Jim Johnson
|
|
|
project under construction
|
Groundwork | 5/3/2006 | 5/3/2006 | 5/4/2006 | P | PART |
Jim Johnson
|
|
|
Phone #: ###-#### Internet Inspection Request from: Ione Coleman groundwork down stream of intercepter test ok ok to cover need first chamber vent on intercepter and sampling port installed
|