Final | 8/23/2006 | 8/24/2006 | 8/24/2006 | A | PASS |
Daryl Spivey
|
|
|
Ready for final. Thanks ... Jannette; Phone #: ###-#### Internet Inspection Request from: Jannette Soden
|
Plumbing Rough-in | 7/6/2006 | 7/6/2006 | 7/6/2006 | A | PASS |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 7/6/2006 at 6:51:55 AM. Contact: ###-####.
|
Plumbing Rough-in | 7/5/2006 | 7/5/2006 | 7/5/2006 | P | PART |
Eric Strole
|
|
|
Scheduled by a contractor via Hello! on 7/5/2006 at 7:52:06 AM. Contact: ###-####.front unit ok-back unit need to test dwv on washer and kitchen.
|
Plumbing Rough-in | 6/29/2006 | 6/30/2006 | 6/30/2006 | P | FAIL |
Bill VanDegrift
|
|
|
Scheduled by a contractor via Hello! on 6/29/2006 at 11:26:02 AM. Contact: ###-####.dwv test failed on both units-need to meet cross-sectional venting on far unit.
|
Groundwork | 5/12/2006 | 5/12/2006 | 5/12/2006 | P | PASS |
Bill VanDegrift
|
|
|
jannette ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|