Final | 12/19/2006 | 12/20/2006 | 12/20/2006 | A | PASS |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 12/19/2006 at 10:28:47 AM. Contact: ###-####.
|
Med/Gas Systems | 12/6/2006 | 12/7/2006 | 12/7/2006 | A | PASS |
Jim Johnson
|
|
|
24 hr pressure test ok
|
Plumbing Rough-in | 12/5/2006 | 12/6/2006 | 12/6/2006 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 12/5/2006 at 4:30:51 PM. Contact: ###-####. repiped med gas location start of 24 hr pressure test
|
Med/Gas Systems | 11/17/2006 | 11/20/2006 | 11/20/2006 | A | PART |
Jim Johnson
|
|
|
24 hr pressure test ok
|
Med/Gas Systems | 11/16/2006 | 11/17/2006 | 11/17/2006 | A | PART |
Jim Johnson
|
|
|
ROUGH IN MED GAS - CALL BILL TO SCHEDULE ON SITE ###-####; Phone #: ###-#### Internet Inspection Request from: Allison Briggs start of 24 hr pressure test of continued piping to mri room
|
Med/Gas Systems | 11/8/2006 | 11/9/2006 | 11/9/2006 | A | PART |
Jim Johnson
|
|
|
24 hr pressure test ok
|
Med/Gas Systems | 11/7/2006 | 11/8/2006 | 11/8/2006 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 11/7/2006 at 2:19:44 PM. Contact: ###-####. start of 24 hr pressure test on med gas
|
Plumbing Rough-in | 10/26/2006 | 10/27/2006 | 10/27/2006 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 10/26/2006 at 4:28:00 PM. Contact: ###-####. in wall rough-in for sink ok ok to cover
|
Plumbing Rough-in | 10/16/2006 | 10/17/2006 | 10/17/2006 | A | PART |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 10/16/2006 at 12:56:50 PM. Contact: ###-####. in wall rough-in for rest room and sink ok ok to cover
|
Groundwork | 9/5/2006 | 9/7/2006 | 9/7/2006 | P | PASS |
Jim Johnson
|
|
|
BILL HARRISON IS ON SITE CALL TO SCHEDULE; Phone #: ###-#### Internet Inspection Request from: Allison Briggs
|