Water and/or Sewer | 5/9/2007 | 5/9/2007 | 5/9/2007 | P | PASS |
Daryl Spivey
|
|
|
Dug up all the way back to c/o behind shed, regraded and rebedded pipe.....
|
DOC - Permit Finaled | 5/9/2007 | 5/9/2007 | 5/9/2007 | P | PASS |
Daryl Spivey
|
|
|
|
Water and/or Sewer | 5/7/2007 | 5/7/2007 | 5/7/2007 | A | NR |
Daryl Spivey
|
|
|
in process of getting a backhoe and redigging to grade piping ........ds
|
Water and/or Sewer | 5/4/2007 | 5/4/2007 | 5/4/2007 | | PEND |
Daryl Spivey
|
|
|
This permit was reopened after problems from installation of new sewer pipe was installed. As far as I could tell the pipe was fairly flat to begin with and was not bedded properly and caused sagging and backup in to the house after a couple of months, the second time......We had Strasser from PW come down and after much discussion the main sewer in the right of way was dug up and Mike installed a new lower elevation stub. Which was on 5/3/07....On 5/4 I checked on progress and the 10 ft. of pipe installed was still flat and was connected to reversed grade pipe at which point I instructed excavator he would have to dig back towards house to expose pipe and relay it until it was grade properly. That is where the problem was left as of 5 pm today...5/4.......ds
|
Water and/or Sewer | 2/16/2007 | 2/16/2007 | 2/16/2007 | P | PASS |
Daryl Spivey
|
|
|
repipe building drain..very complicated mess......ds
|
DOC - Permit Finaled | 2/16/2007 | 2/16/2007 | 2/16/2007 | P | PASS |
Daryl Spivey
|
|
|
repipe building drain...ds
|
Water and/or Sewer | 1/29/2007 | 1/30/2007 | 1/30/2007 | A | PASS |
Daryl Spivey
|
|
|
jason; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
DOC - Permit Finaled | 1/30/2007 | 1/30/2007 | 1/30/2007 | A | PASS |
Daryl Spivey
|
|
|
jason; Phone #: ###-#### Internet Inspection Request from: Victoria Beall sewer line replaced...ABS...ds
|