Final | 1/22/2008 | 1/23/2008 | 1/23/2008 | A | PASS |
Jim Johnson
|
|
|
|
Final | 1/21/2008 | 1/22/2008 | 1/22/2008 | P | CANC |
Jim Johnson
|
|
|
Colin Libby is the field contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet
|
Final | 1/15/2008 | 1/16/2008 | 1/16/2008 | P | PART |
Jim Johnson
|
|
|
Colin Libby is the field contact. He would like the inspection be later in the afternoon. Thanks! Phone #: ###-#### Internet Inspection Request from: Heidi Mallet need to provide RP for coffee and tea brewer,s
|
Final | 1/14/2008 | 1/15/2008 | 1/15/2008 | P | CANC |
Jim Johnson
|
|
|
Colin Libby is the field contact. He would like his inspection to be later in the afternoon. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet canc. by colin libby
|
Final | 1/4/2008 | 1/7/2008 | 1/7/2008 | P | PART |
Jim Johnson
|
|
|
made walk through with colin second floor
|
Final | 1/3/2008 | 1/4/2008 | 1/4/2008 | P | PART |
Jim Johnson
|
|
|
Colin; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt walked first floor with Colin
|
Med/Gas Systems | 10/23/2007 | 10/24/2007 | 10/24/2007 | A | PART |
Jim Johnson
|
|
|
24 HR. PRESSURE TEST OK
|
Med/Gas Systems | 10/22/2007 | 10/23/2007 | 10/23/2007 | A | PART |
Jim Johnson
|
|
|
Colin Libby is the field contact. For 2nd floor. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet start of 24 hr pressure test on total med gas system
|
Plumbing Rough-in | 10/11/2007 | 10/12/2007 | 10/12/2007 | P | PART |
Jim Johnson
|
|
|
Plumbing & Med Gas Rough In. Colin Libby is the field contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet start of west side second floor 24 hr test water in middle section second floor test ok
|
Plumbing Rough-in | 10/10/2007 | 10/11/2007 | 10/11/2007 | A | PART |
Bill VanDegrift
|
|
|
early partial water mains and west wing 2nd floor and center dwv
|
Plumbing Rough-in | 10/10/2007 | 10/10/2007 | 10/10/2007 | P | CANC |
Bill VanDegrift
|
|
|
Partial rough in requested. Colin Libby is the field contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet contractor called and canceled.
|
Med/Gas Systems | 10/9/2007 | 10/10/2007 | 10/10/2007 | A | PASS |
Lee Rice
|
|
|
gages on second floor south-east side of building contact J T installer
|
Med/Gas Systems | 10/8/2007 | 10/9/2007 | 10/9/2007 | A | PART |
Jim Johnson
|
|
|
Colin Libby is the field contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet start of 24 hr pressure test east side of building
|
Plumbing Rough-in | 10/5/2007 | 10/8/2007 | 10/8/2007 | A | CANC |
Jim Johnson
|
|
|
Partial rough-in for med gas and plumbing. Field contact is Colin Libby. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet water on second floor east wing test ok
|
Med/Gas Systems | 10/3/2007 | 10/4/2007 | 10/4/2007 | A | PART |
Jim Johnson
|
|
|
Colin Libby is the field contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet 24 hr pressure test start on run,s on west side note DWV on west side test ok still need to run water lines
|
Plumbing Rough-in | 10/3/2007 | 10/4/2007 | 10/4/2007 | A | PART |
Jim Johnson
|
|
|
Colin Libby is the field contact Phone #: ###-#### Internet Inspection Request from: Heidi Mallet roof and over flow drain,s on east side of building test ok DWV on east side second floor test ok still working on water
|
Med/Gas Systems | 10/3/2007 | 10/3/2007 | 10/3/2007 | P | CANC |
Jim Johnson
|
|
|
Colin Libby is the field contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet south east corner start of 24 hr pressure test second floor
|
Plumbing Rough-in | 10/3/2007 | 10/3/2007 | 10/3/2007 | P | PART |
Jim Johnson
|
|
|
Colin Libby is the field contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet water and dwv second floor south east corner test ok
|
Plumbing Rough-in | 9/26/2007 | 9/27/2007 | 9/27/2007 | A | PART |
Jim Johnson
|
|
|
roof and over flow drain,s on west side of building and drain,e in middle section on north side test ok water and DWV
|
Plumbing Rough-in | 9/25/2007 | 9/26/2007 | 9/26/2007 | A | PART |
Jim Johnson
|
|
|
Partial plumbing rough-in inspection. Colin Libby is the field contact. ###-####. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet dwv and water west wing test ok
|
Med/Gas Systems | 9/24/2007 | 9/25/2007 | 9/25/2007 | P | PART |
Jim Johnson
|
|
|
24 hr. pressure test on med gas second floor west wing test ok
|
Med/Gas Systems | 9/21/2007 | 9/24/2007 | 9/24/2007 | P | CANC |
Jim Johnson
|
|
|
Colin Libby is field contact. Partial rough-in inspection for 2nd floor on med gas. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet note start of 24 hr. pressure test on med gas west wing second floor
|
Plumbing Rough-in | 9/20/2007 | 9/21/2007 | 9/21/2007 | A | PART |
Jim Johnson
|
|
|
Colin Libby is the contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet need to repipe two shower to correct tailpiece distance not to exceed 24 inches in length
|
Plumbing Rough-in | 9/20/2007 | 9/21/2007 | 9/20/2007 | P | CANC |
Jim Johnson
|
|
|
Colin is the contact Phone #: ###-#### Internet Inspection Request from: Heidi Mallet Inspection cancelled from web by: Heidi Mallet
|
Med/Gas Systems | 9/17/2007 | 9/18/2007 | 9/18/2007 | A | PART |
Eric Strole
|
|
|
test on med gas for 1st flr pass.
|
Med/Gas Systems | 9/14/2007 | 9/17/2007 | 9/17/2007 | A | PART |
Eric Strole
|
|
|
Colin Libby is the field contatct. Partial Med Gas Rough In inspection. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-this is the start of 24 hr test for 1st flr on med gas system.
|
Plumbing Rough-in | 9/11/2007 | 9/12/2007 | 9/12/2007 | A | NR |
Eric Strole
|
|
|
|
Plumbing Rough-in | 9/11/2007 | 9/11/2007 | 9/11/2007 | P | PART |
Eric Strole
|
|
|
Colin Libby is the field contact. We need a partial rough in inspection on the 1st floor. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-section of r/i complete is marked on plans.
|
Plumbing Rough-in | 9/6/2007 | 9/7/2007 | 9/7/2007 | P | PART |
Eric Strole
|
|
|
Colin Libby is the field contact. Partial rough in inspection on 1st floor and partial for 1st floor ceiling. Phone #: ###-#### Internet Inspection Request from: Heidi -Mallet-dwv & water complete is marked on plans.
|
Plumbing Rough-in | 9/4/2007 | 9/4/2007 | 9/4/2007 | P | PART |
Eric Strole
|
|
|
sections of dwv & water complete is marked on plans in job trailer.
|
Plumbing Rough-in | 8/31/2007 | 9/4/2007 | 9/4/2007 | A | PART |
Eric Strole
|
|
|
need to nailplate.
|
Plumbing Rough-in | 8/30/2007 | 8/31/2007 | 8/31/2007 | P | PART |
Eric Strole
|
|
|
Colin Libby is the field contact. We need a partial above ground inspection. Thanks Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-need to use mission couplings from pvc to cast iron, missing nailplates.
|
Med/Gas Systems | 8/28/2007 | 8/29/2007 | 8/29/2007 | A | PART |
Eric Strole
|
|
|
24 hr test on section of med gas pass.
|
Med/Gas Systems | 8/27/2007 | 8/28/2007 | 8/28/2007 | A | PART |
Eric Strole
|
|
|
Colin Libby is the field contact. We need a 24hr pressure test done on area one on the first floor on Tuesday 8/28/07. Thank you Phone #: ###-#### Internet Inspection -Request from: Heidi Mallet-south west outlet box on 1st flr to above 2nd outlet box start 24 hr test.
|
Med/Gas Systems | 7/19/2007 | 7/19/2007 | 7/19/2007 | P | PART |
Eric Strole
|
|
|
outside underground oxygen line is labeled, ok to cover.
|
Other | 7/6/2007 | 7/9/2007 | 7/9/2007 | A | CANC |
Eric Strole
|
|
|
|
Med/Gas Systems | 7/5/2007 | 7/5/2007 | 7/5/2007 | P | PART |
Eric Strole
|
|
|
pressure test on oxygen line from outside building to equipment room pass, still needs to labeled before backfill.
|
Med/Gas Systems | 7/3/2007 | 7/5/2007 | 7/5/2007 | A | CANC |
Eric Strole
|
|
|
|
Med/Gas Systems | 7/2/2007 | 7/3/2007 | 7/3/2007 | A | PART |
Eric Strole
|
|
|
Colin Libby is the field contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-this is the start of 24 hr test on oxygen from outside feed to inside equipment room, test gage at 150 psi.
|
Groundwork | 6/21/2007 | 6/22/2007 | 6/22/2007 | A | PASS |
Lee Rice
|
|
|
Colin Libby is the field contact. Domestic water and roof drain inspection needed. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet......storm sewer stubs and main water ok to cover.....stubs test with mains.
|
Groundwork | 6/19/2007 | 6/19/2007 | 6/19/2007 | P | PART |
Eric Strole
|
|
|
Colin Libby is the field contact. Partial ground inspection. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-sanitary & grease waste ground work complete(pass)still need water line & roof drain tie in's.
|
Other | 6/15/2007 | 6/18/2007 | 6/18/2007 | A | PART |
Jim Johnson
|
|
|
portion of ground work inspected on 6/15 /07 test ok will up date planes on next inspectionas per conversation with Colin from ridgeway
|
Groundwork | 6/15/2007 | 6/15/2007 | 6/15/2007 | P | PART |
Eric Strole
|
|
|
Colin Libby is the field contact. Needs a partial ground rough in inspection. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-section of g/w on test pass.
|
Groundwork | 6/13/2007 | 6/13/2007 | 6/13/2007 | P | PART |
Eric Strole
|
|
|
Colin Libby is the field contact. Needs a partial ground inspection. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-section of ground work complete is marked on plans in job office.
|
Groundwork | 6/6/2007 | 6/7/2007 | 6/7/2007 | P | PART |
Bill VanDegrift
|
|
|
west centeral gw ok marked on plans. needs roof drains.
|
Groundwork | 6/6/2007 | 6/6/2007 | 6/6/2007 | P | PART |
Eric Strole
|
|
|
Colin Libby is the field contact. Partial ground inspection. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-sections of g/w complete is marked on plans in job office.
|
Groundwork | 5/24/2007 | 5/25/2007 | 5/25/2007 | P | PART |
Bill VanDegrift
|
|
|
Colin Libby is the field contact. Grease Trap. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet interceptor test and piping ok to cover
|
Groundwork | 5/24/2007 | 5/25/2007 | 5/25/2007 | A | PART |
Eric Strole
|
|
|
Colin Libby is the field contact. Grease Trap Inspection Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-this was the start of test on grease trap.
|
Groundwork | 5/23/2007 | 5/23/2007 | 5/23/2007 | P | PART |
Jim Johnson
|
|
|
Colin Libby is the field contact. Partial udnerground inspection. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet kit grease trunk line south east corner of building test ok
|
Groundwork | 5/22/2007 | 5/23/2007 | 5/23/2007 | A | FAIL |
Jim Johnson
|
|
|
Colin Libby as field contact. Partial underground inspection. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet test failed on DWV portion of trunk grease line in south east side of building need to retest contractor to recall when ready
|
Groundwork | 5/18/2007 | 5/21/2007 | 5/21/2007 | A | PART |
Jim Johnson
|
|
|
Colin Libby is the field contact. Partial Inspection for the groundwork. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet portion of trunk lines noted and dated on approved set of plan,s in general construction trailer test ok
|