Information based on query as of Monday, July 1, 2024.
Permit Information
Permit NumberPLM07-01562
StatusFinaled
Name RIDGEWAY INDUSTRIAL INC
Site Address 6651 W FRANKLIN RD
Project Name 
Customer Number5187
ePlanReview 
Description
Plumbing Permit - New: Under ground and above ground plumbing
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final1/22/20081/23/20081/23/2008APASS
DetailsJim Johnson
Final1/21/20081/22/20081/22/2008PCANC
DetailsJim Johnson
Colin Libby is the field contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet
Final1/15/20081/16/20081/16/2008PPART
DetailsJim Johnson
Colin Libby is the field contact. He would like the inspection be later in the afternoon.
Thanks! Phone #: ###-#### Internet Inspection Request from: Heidi Mallet need to provide RP for coffee and tea brewer,s
Final1/14/20081/15/20081/15/2008PCANC
DetailsJim Johnson
Colin Libby is the field contact. He would like his inspection to be later in the afternoon. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet canc. by colin libby
Final1/4/20081/7/20081/7/2008PPART
DetailsJim Johnson
made walk through with colin second floor
Final1/3/20081/4/20081/4/2008PPART
DetailsJim Johnson
Colin; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt walked first floor with Colin
Med/Gas Systems10/23/200710/24/200710/24/2007APART
DetailsJim Johnson
24 HR. PRESSURE TEST OK
Med/Gas Systems10/22/200710/23/200710/23/2007APART
DetailsJim Johnson
Colin Libby is the field contact. For 2nd floor. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet start of 24 hr pressure test on total med gas system
Plumbing Rough-in10/11/200710/12/200710/12/2007PPART
DetailsJim Johnson
Plumbing & Med Gas Rough In. Colin Libby is the field contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet start of west side second floor 24 hr test water in middle section second floor test ok
Plumbing Rough-in10/10/200710/11/200710/11/2007APART
DetailsBill VanDegrift
early partial water mains and west wing 2nd floor and center dwv
Plumbing Rough-in10/10/200710/10/200710/10/2007PCANC
DetailsBill VanDegrift
Partial rough in requested. Colin Libby is the field contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet contractor called and canceled.
Med/Gas Systems10/9/200710/10/200710/10/2007APASS
DetailsLee Rice
gages on second floor south-east side of building contact J T installer
Med/Gas Systems10/8/200710/9/200710/9/2007APART
DetailsJim Johnson
Colin Libby is the field contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet start of 24 hr pressure test east side of building
Plumbing Rough-in10/5/200710/8/200710/8/2007ACANC
DetailsJim Johnson
Partial rough-in for med gas and plumbing. Field contact is Colin Libby. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet water on second floor east wing test ok
Med/Gas Systems10/3/200710/4/200710/4/2007APART
DetailsJim Johnson
Colin Libby is the field contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet 24 hr pressure test start on run,s on west side note DWV on west side test ok still need to run water lines
Plumbing Rough-in10/3/200710/4/200710/4/2007APART
DetailsJim Johnson
Colin Libby is the field contact Phone #: ###-#### Internet Inspection Request from: Heidi Mallet roof and over flow drain,s on east side of building test ok DWV on east side second floor test ok still working on water
Med/Gas Systems10/3/200710/3/200710/3/2007PCANC
DetailsJim Johnson
Colin Libby is the field contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet south east corner start of 24 hr pressure test second floor
Plumbing Rough-in10/3/200710/3/200710/3/2007PPART
DetailsJim Johnson
Colin Libby is the field contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet water and dwv second floor south east corner test ok
Plumbing Rough-in9/26/20079/27/20079/27/2007APART
DetailsJim Johnson
roof and over flow drain,s on west side of building and drain,e in middle section on north side test ok water and DWV
Plumbing Rough-in9/25/20079/26/20079/26/2007APART
DetailsJim Johnson
Partial plumbing rough-in inspection. Colin Libby is the field contact. ###-####. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet dwv and water west wing test ok
Med/Gas Systems9/24/20079/25/20079/25/2007PPART
DetailsJim Johnson
24 hr. pressure test on med gas second floor west wing test ok
Med/Gas Systems9/21/20079/24/20079/24/2007PCANC
DetailsJim Johnson
Colin Libby is field contact. Partial rough-in inspection for 2nd floor on med gas. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet note start of 24 hr. pressure test on med gas west wing second floor
Plumbing Rough-in9/20/20079/21/20079/21/2007APART
DetailsJim Johnson
Colin Libby is the contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet need to repipe two shower to correct tailpiece distance not to exceed 24 inches in length
Plumbing Rough-in9/20/20079/21/20079/20/2007PCANC
DetailsJim Johnson
Colin is the contact Phone #: ###-#### Internet Inspection Request from: Heidi Mallet Inspection cancelled from web by: Heidi Mallet
Med/Gas Systems9/17/20079/18/20079/18/2007APART
DetailsEric Strole
test on med gas for 1st flr pass.
Med/Gas Systems9/14/20079/17/20079/17/2007APART
DetailsEric Strole
Colin Libby is the field contatct. Partial Med Gas Rough In inspection. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-this is the start of 24 hr test for 1st flr on med gas system.
Plumbing Rough-in9/11/20079/12/20079/12/2007ANR
DetailsEric Strole
Plumbing Rough-in9/11/20079/11/20079/11/2007PPART
DetailsEric Strole
Colin Libby is the field contact. We need a partial rough in inspection on the 1st floor. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-section of r/i complete is marked on plans.
Plumbing Rough-in9/6/20079/7/20079/7/2007PPART
DetailsEric Strole
Colin Libby is the field contact. Partial rough in inspection on 1st floor and partial for 1st floor ceiling. Phone #: ###-#### Internet Inspection Request from: Heidi -Mallet-dwv & water complete is marked on plans.
Plumbing Rough-in9/4/20079/4/20079/4/2007PPART
DetailsEric Strole
sections of dwv & water complete is marked on plans in job trailer.
Plumbing Rough-in8/31/20079/4/20079/4/2007APART
DetailsEric Strole
need to nailplate.
Plumbing Rough-in8/30/20078/31/20078/31/2007PPART
DetailsEric Strole
Colin Libby is the field contact. We need a partial above ground inspection. Thanks Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-need to use mission couplings from pvc to cast iron, missing nailplates.
Med/Gas Systems8/28/20078/29/20078/29/2007APART
DetailsEric Strole
24 hr test on section of med gas pass.
Med/Gas Systems8/27/20078/28/20078/28/2007APART
DetailsEric Strole
Colin Libby is the field contact. We need a 24hr pressure test done on area one on the first floor on Tuesday 8/28/07. Thank you Phone #: ###-#### Internet Inspection -Request from: Heidi Mallet-south west outlet box on 1st flr to above 2nd outlet box start 24 hr test.
Med/Gas Systems7/19/20077/19/20077/19/2007PPART
DetailsEric Strole
outside underground oxygen line is labeled, ok to cover.
Other7/6/20077/9/20077/9/2007ACANC
DetailsEric Strole
Med/Gas Systems7/5/20077/5/20077/5/2007PPART
DetailsEric Strole
pressure test on oxygen line from outside building to equipment room pass, still needs to labeled before backfill.
Med/Gas Systems7/3/20077/5/20077/5/2007ACANC
DetailsEric Strole
Med/Gas Systems7/2/20077/3/20077/3/2007APART
DetailsEric Strole
Colin Libby is the field contact. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-this is the start of 24 hr test on oxygen from outside feed to inside equipment room, test gage at 150 psi.
Groundwork6/21/20076/22/20076/22/2007APASS
DetailsLee Rice
Colin Libby is the field contact. Domestic water and roof drain inspection needed. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet......storm sewer stubs and main water ok to cover.....stubs test with mains.
Groundwork6/19/20076/19/20076/19/2007PPART
DetailsEric Strole
Colin Libby is the field contact. Partial ground inspection. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-sanitary & grease waste ground work complete(pass)still need water line & roof drain tie in's.
Other6/15/20076/18/20076/18/2007APART
DetailsJim Johnson
portion of ground work inspected on 6/15 /07 test ok will up date planes on next inspectionas per conversation with Colin from ridgeway
Groundwork6/15/20076/15/20076/15/2007PPART
DetailsEric Strole
Colin Libby is the field contact. Needs a partial ground rough in inspection. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-section of g/w on test pass.
Groundwork6/13/20076/13/20076/13/2007PPART
DetailsEric Strole
Colin Libby is the field contact. Needs a partial ground inspection. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-section of ground work complete is marked on plans in job office.
Groundwork6/6/20076/7/20076/7/2007PPART
DetailsBill VanDegrift
west centeral gw ok marked on plans. needs roof drains.
Groundwork6/6/20076/6/20076/6/2007PPART
DetailsEric Strole
Colin Libby is the field contact. Partial ground inspection. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-sections of g/w complete is marked on plans in job office.
Groundwork5/24/20075/25/20075/25/2007PPART
DetailsBill VanDegrift
Colin Libby is the field contact. Grease Trap. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet interceptor test and piping ok to cover
Groundwork5/24/20075/25/20075/25/2007APART
DetailsEric Strole
Colin Libby is the field contact. Grease Trap Inspection Phone #: ###-#### Internet Inspection Request from: Heidi Mallet-this was the start of test on grease trap.
Groundwork5/23/20075/23/20075/23/2007PPART
DetailsJim Johnson
Colin Libby is the field contact. Partial udnerground inspection. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet kit grease trunk line south east corner of building test ok
Groundwork5/22/20075/23/20075/23/2007AFAIL
DetailsJim Johnson
Colin Libby as field contact. Partial underground inspection. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet test failed on DWV portion of trunk grease line in south east side of building need to retest contractor to recall when ready
Groundwork5/18/20075/21/20075/21/2007APART
DetailsJim Johnson
Colin Libby is the field contact. Partial Inspection for the groundwork. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet portion of trunk lines noted and dated on approved set of plan,s in general construction trailer test ok