Final | 1/11/2008 | 1/14/2008 | 1/14/2008 | A | PASS |
Jim Johnson
|
|
|
shawn Phone #: ###-####
|
Final | 1/8/2008 | 1/8/2008 | 1/8/2008 | P | PART |
Jim Johnson
|
|
|
shawn Phone #: ###-#### need to provide building premise protection installed on building water supply line (double check ) and expansion tank for thermal expansion control oked temp for T I space
|
Final | 1/4/2008 | 1/7/2008 | 1/7/2008 | A | PART |
Jim Johnson
|
|
|
sean Phone #: ###-#### need RP for dishwasher need RP for soda machine need to anchor prep sink and caulk to wall
|
Plumbing Rough-in | 12/13/2007 | 12/14/2007 | 12/14/2007 | A | PART |
Jim Johnson
|
|
|
shawn Phone #: ###-#### in wall rough-in test ok ok to cover note need to find source of existing 3/4 water service to T.I. space to determine fixture loading may have ti increase line size if required
|
Plumbing Rough-in | 12/12/2007 | 12/13/2007 | 12/13/2007 | A | PART |
Jim Johnson
|
|
|
ron Phone #: ###-#### unable to find an approved set of plan,s on site called contractor will reschedule when plan,s are on site
|