Final | 6/13/2008 | 6/16/2008 | 6/16/2008 | A | PASS |
Daryl Spivey
|
|
|
FINAL SPIRIT DIST JOHN B ###-#### Phone #: ###-#### Internet Inspection Request from: Allison Briggs
|
Other | 6/6/2008 | 6/6/2008 | 6/6/2008 | A | PASS |
Bill VanDegrift
|
|
|
existing roof drains are connected will add overflow over the office.
|
Other | 6/2/2008 | 6/2/2008 | 6/2/2008 | P | PEND |
Eric Strole
|
|
|
need secondary roof drainage above office area by final plumbing inspection.
|
Final | 5/16/2008 | 5/16/2008 | 5/16/2008 | P | PART |
Bill VanDegrift
|
|
|
spirit final - call john to schedule ###-#### Phone #: ###-#### Internet Inspection Request from: Allison Briggs temp occ for main office ok.
|
Plumbing Rough-in | 5/8/2008 | 5/9/2008 | 5/9/2008 | A | PASS |
Eric Strole
|
|
|
ROUGH IN AT SPIRIT CALL ROGER TO SCHEDULE ###-#### Phone #: ###-#### Internet Inspection Request from: Allison Briggs-this was for running new buildind drain to lift station. need drawings of work by final.
|
Plumbing Rough-in | 4/18/2008 | 4/21/2008 | 4/21/2008 | A | PART |
Bill VanDegrift
|
|
|
CALL ROGER TO SCHEDULE - ROUGH IN AT SPIRIT Phone #: ###-#### Internet Inspection Request from: Allison Briggs hose bibs in new office area.
|
Plumbing Rough-in | 4/17/2008 | 4/17/2008 | 4/17/2008 | A | PART |
Bill VanDegrift
|
|
|
rough in at Spirit Dist - Call Roger to schedule ###-#### Phone #: ###-#### Internet Inspection Request from: Allison Briggs added 1-bar sink in class room, ok o cover wall. not tied in in the crawl space.
|
Final | 4/11/2008 | 4/11/2008 | 4/11/2008 | P | PART |
Bill VanDegrift
|
|
|
FINAL FOR SPIRIT - CALL ROGER ELAM ###-#### Phone #: ###-#### Internet Inspection Request from: Allison Briggs will call office ok to occupy
|
Plumbing Rough-in | 3/19/2008 | 3/20/2008 | 3/20/2008 | A | PART |
Eric Strole
|
|
|
recoup sink pass.
|
Plumbing Rough-in | 3/19/2008 | 3/19/2008 | 3/19/2008 | P | FAIL |
Eric Strole
|
|
|
plumbing rough in - call Roger to schedule ###-#### Phone #: ###-#### Internet Inspection Request from: Allison Briggs-dwv test failed.
|
Plumbing Rough-in | 3/6/2008 | 3/6/2008 | 3/6/2008 | A | FAIL |
Bill VanDegrift
|
|
|
it has been brought to my attention that material that does not comply wiyh section 701.1.2 of the 2003 upc has been installed in a return air plenum. remove and replace with approved material.
|
Plumbing Rough-in | 2/29/2008 | 2/29/2008 | 2/29/2008 | P | PART |
Bill VanDegrift
|
|
|
CALL ROGER TO SCHEDULE ###-#### ROUGH IN Phone #: ###-#### Internet Inspection Request from: Allison Briggs warehouse restroom area ok pending approved plans.
|
Plumbing Rough-in | 2/7/2008 | 2/8/2008 | 2/8/2008 | A | PASS |
Eric Strole
|
|
|
SPIRIT DIST - CALL ROGER TO SCHEDULE ###-#### PLUMBING ROUGH IN Phone #: ###-#### Internet Inspection Request from: Allison Briggs-ground work for warehouse restrooms pass.
|
Groundwork | 2/1/2008 | 2/4/2008 | 2/4/2008 | A | PASS |
Eric Strole
|
|
|
PLEASE CALL ROGER TO SCHEDULE GROUNDWORK AT SPIRIT DIST ###-#### Phone #: ###-#### Internet Inspection Request from: Allison Briggs-ground word for recovery sink pass.
|
Plumbing Rough-in | 1/31/2008 | 2/1/2008 | 2/1/2008 | P | PART |
Eric Strole
|
|
|
Spirit Distributing rough in plumbing inspection, Call Roger Elam to schedule Phone #: ###-#### Internet Inspection Request from: Allison Briggs-main office area r/i pass, ok to cover.
|
Plumbing Rough-in | 1/25/2008 | 1/28/2008 | 1/28/2008 | A | PART |
Eric Strole
|
|
|
PARTIAL ROUGH IN PLEASE CALL ROGER E TO SCHEDULE ###-#### Phone #: ###-#### Internet Inspection Request from: Allison Briggs-part ground work from 4" tie in to stub into future bathroom group.
|