Final | 5/22/2008 | 5/22/2008 | 5/22/2008 | P | PASS |
Bill VanDegrift
|
|
|
final ok
|
Final | 5/22/2008 | 5/22/2008 | 5/22/2008 | P | CANC |
Bill VanDegrift
|
|
|
verify water heater installation
|
Final | 5/22/2008 | 5/22/2008 | 5/22/2008 | A | PART |
Bill VanDegrift
|
|
|
All water heater equipment is up and running for the mixing valves. Phone #: ###-#### Internet Inspection Request from: Kirk Johns water heater vent needs attention
|
Final | 5/21/2008 | 5/21/2008 | 5/21/2008 | P | PART |
Jim Johnson
|
|
|
Jim the water line is capped off if you are in the area at any time please stop. thanks kirk johns Phone #: ###-#### Internet Inspection Request from: Kirk Johns visual on water line that was capped off and tie in for sprinkler ok ok to cover
|
Final | 5/16/2008 | 5/19/2008 | 5/19/2008 | P | PART |
Jim Johnson
|
|
|
plumbing final for proqect if any questons please call. thanks Phone #: ###-#### Internet Inspection Request from: Kirk Johns need to adjust all faucets for 120 degree hot water limitation provide identification tag,s for all backflow devices cap and remove old existing water line caulk all fixtures contractor to recall when ready oked temp.
|
Plumbing Rough-in | 4/4/2008 | 4/4/2008 | 4/4/2008 | P | PASS |
Jim Johnson
|
|
|
josh Phone #: ###-####
|
Water and/or Sewer | 3/6/2008 | 3/7/2008 | 3/7/2008 | A | PASS |
Jim Johnson
|
|
|
Grease interceptor full of water. Phone #: ###-#### Internet Inspection Request from: Kirk Johns
|
Groundwork | 3/6/2008 | 3/6/2008 | 3/6/2008 | A | PART |
Jim Johnson
|
|
|
Underground of the grease interceptor outside the building Phone #: ###-#### Internet Inspection Request from: Kirk Johns piping for interceptor outside building test ok need to test interceptor need to fill with water contractor to recall when ready
|
Groundwork | 2/25/2008 | 2/26/2008 | 2/26/2008 | A | PASS |
Jim Johnson
|
|
|
any questions please call. Underground of sewer and grease and water stubbed outside. Phone #: ###-#### Internet Inspection Request from: Kirk Johns
|