Final | 10/29/2008 | 10/29/2008 | 10/29/2008 | P | PASS |
Eric Strole
|
|
|
Scheduled by a contractor via Hello! on 10/29/2008 at 7:12:40 AM. Contact: ###-####.
|
Final | 10/27/2008 | 10/28/2008 | 10/28/2008 | A | PART |
Eric Strole
|
|
|
Scheduled by a contractor via Hello! on 10/27/2008 at 3:46:55 PM. Contact: ###-####.-need dbca upstream of booster pump.
|
Plumbing Rough-in | 8/28/2008 | 8/29/2008 | 8/29/2008 | A | PASS |
Eric Strole
|
|
|
mary Phone #: ###-####
|
Plumbing Rough-in | 8/27/2008 | 8/28/2008 | 8/28/2008 | A | PART |
Eric Strole
|
|
|
Scheduled by a contractor via Hello! on 8/27/2008 at 1:43:01 PM. Contact: ###-####. can only have 3 toilets on a 3" horizontal drain. pex needs to be at least 6" from can lights. tent all overhead waterlines.
|
Plumbing Rough-in | 8/26/2008 | 8/27/2008 | 8/27/2008 | P | CANC |
Eric Strole
|
|
|
Scheduled by a contractor via Hello! on 8/26/2008 at 1:31:08 PM. Contact: ###-####. Inspection cancelled from web by: Alexandra Rahn
|