Final | 1/30/2009 | 1/30/2009 | 1/30/2009 | P | PASS |
Eric Strole
|
|
|
rusty Phone #: ###-####
|
PLM-Aging Inspection | 12/1/2008 | 12/1/2008 | 12/1/2008 | | PASS |
Eric Strole
|
|
|
|
Med/Gas Systems | 9/30/2008 | 10/1/2008 | 10/1/2008 | P | PASS |
Eric Strole
|
|
|
eric
|
Plumbing Rough-in | 9/30/2008 | 10/1/2008 | 10/1/2008 | P | PASS |
Eric Strole
|
|
|
eric
|
Med/Gas Systems | 9/30/2008 | 9/30/2008 | 9/30/2008 | P | PART |
Eric Strole
|
|
|
eric-this is the start of 24 hr test on vac & compressed air. vac is on 5 psi, air is on 60 psi.
|
Plumbing Rough-in | 9/30/2008 | 9/30/2008 | 9/30/2008 | P | PART |
Eric Strole
|
|
|
rusty Phone #: ###-####-dwv test failed, water test pass, need to use approved drainage fitting for lav pulled off side inlet in crawl.
|
Other | 9/22/2008 | 9/22/2008 | 9/22/2008 | P | DONE |
Eric Strole
|
|
|
conference-plumber will call when rough-in is ready, vac & air will be in crawl & outside walls so told plumber i will give him a ok to cover when dwv & water is complete.
|
Other | 9/3/2008 | 9/3/2008 | 9/3/2008 | P | DONE |
Eric Strole
|
|
|
conference - 2:30 -this was a conferance on changes to plans, will get letter.
|