Final | 3/17/2009 | 3/17/2009 | 3/17/2009 | P | PASS |
Jim Johnson
|
|
|
come to the noth side to the construction trailor and get with Chris Pallmer to get into the building ###-#### Phone #: ###-#### Internet Inspection Request from: Kirk Johns
|
Final | 1/28/2009 | 1/28/2009 | 1/28/2009 | P | PART |
Jim Johnson
|
|
|
Jake will be on site so call him so he can meet you and walk the building thanks Kirk Johns Phone #: ###-#### Internet Inspection Request from: Kirk Johns oked temp.
|
Plumbing Rough-in | 12/15/2008 | 12/16/2008 | 12/16/2008 | P | PART |
Jim Johnson
|
|
|
Partial roof drains and rough in of new pipping underground and locker rooms please get with Jake to do a walk around thanks Kirk Johns Phone #: ###-#### Internet Inspection Request from: Kirk Johns D W V and water on new ground work locker room rough-in and new roof and overflow drain,s on north side test ok
|
Plumbing Rough-in | 12/15/2008 | 12/15/2008 | 12/15/2008 | P | CANC |
Jim Johnson
|
|
|
Partional for roof drains, underground for change order locker room. Get with Jake for walk thru Phone #: ###-#### Internet Inspection Request from: Kirk Johns Inspection cancelled from web by: Kirk Johns
|
Roof Drains | 12/8/2008 | 12/8/2008 | 12/8/2008 | P | PART |
Jim Johnson
|
|
|
A patial on the roof drains south west end of building Phone #: ###-#### Internet Inspection Request from: Kirk Johns new roof and over flowv drain,s on south side test ok
|
Plumbing Rough-in | 11/25/2008 | 11/26/2008 | 11/26/2008 | A | PART |
Jim Johnson
|
|
|
please call if any questions thanks Jake Phone #: ###-#### Internet Inspection Request from: Kirk Johns DWV on south and west side except for two sink,s test ok water on south and west side except for two sink,s and trunk line,s test ok
|
Groundwork | 9/29/2008 | 9/29/2008 | 9/29/2008 | P | PASS |
Jim Johnson
|
|
|
Call if you have any questions or concerns Phone #: ###-#### Internet Inspection Request from: Kirk Johns last of ground work test ok storm drain stub out,s test ok
|
Groundwork | 9/24/2008 | 9/25/2008 | 9/25/2008 | A | PART |
Jim Johnson
|
|
|
plumbing of underground for south side bath rooms any questions or concers please call Jake Schwandt ###-#### Phone #: ###-#### Internet Inspection Request from: Kirk Johns rest room,s on south side test ok on D W V
|
Groundwork | 9/23/2008 | 9/24/2008 | 9/24/2008 | A | PART |
Jim Johnson
|
|
|
Ispection for portion of ground work on North side of building. Phone #: ###-#### Internet Inspection Request from: Kirk Johns two inch D W V drain line up to break room sink,s and drinking fountain test ok
|
Water and/or Sewer | 9/19/2008 | 9/19/2008 | 9/19/2008 | P | PART |
Jim Johnson
|
|
|
Parcial underground for sanitary sewer piping Call if you have any questions Phone #: ###-#### Internet Inspection Request from: Kirk Johnstrunk line on east side of building test ok gave verbal ok to cover
|
Water and/or Sewer | 9/8/2008 | 9/9/2008 | 9/9/2008 | A | PASS |
Jim Johnson
|
|
|
Ran the new sewer line in to building from exsisting stub Phone #: ###-#### Internet Inspection Request from: Kirk Johns eight feet of new sewer line test ok
|