Final | 4/24/2009 | 4/27/2009 | 4/27/2009 | A | PASS |
Jim Johnson
|
|
|
Raul Phone #: ###-####
|
Final | 4/2/2009 | 4/3/2009 | 4/3/2009 | A | FAIL |
Jim Johnson
|
|
|
Scheduled by a contractor via Hello! on 4/2/2009 at 3:42:53 PM. upc 601.2, 601.2.1, 601.2.2 2003 need to provide approved identification for the non potable andpoyable water system upc 603.4.12 identification for non-potable water piping note re-circ. on hot water line still tied to non pot-able system . note need to correct hot and cold to correspond with marking,s on faucet ( 3 existing sink,s ) upc 416.0 2003 left correction notice with general contractor on site
|
Final | 3/5/2009 | 3/5/2009 | 3/5/2009 | P | CANC |
Jim Johnson
|
|
|
|
Water and/or Sewer | 3/5/2009 | 3/5/2009 | 3/5/2009 | P | CANC |
Jim Johnson
|
|
|
Phone #: ###-#### Internet Inspection Request from: raul castanon
|
Final | 3/5/2009 | 3/5/2009 | 3/5/2009 | P | PART |
Jim Johnson
|
|
|
made walk through with plumbing contractor on what need to be finished in forensics area for final oked temp occ.
|
Other | 2/25/2009 | 2/27/2009 | 2/27/2009 | A | PART |
Jim Johnson
|
|
|
made walk through with bill t with united water on cross control connection
|
Final | 2/25/2009 | 2/25/2009 | 2/25/2009 | P | NR |
Jim Johnson
|
|
|
Final inspection with the exception of the forensics lab. Phone #: ###-#### Internet Inspection Request from: raul castanon not ready
|
PLM-Aging Inspection | 2/17/2009 | 2/17/2009 | 2/17/2009 | | PASS |
Jim Johnson
|
|
|
project under construction
|
Groundwork | 12/18/2008 | 12/18/2008 | 12/18/2008 | P | PART |
Jim Johnson
|
|
|
Phone #: ###-#### Internet Inspection Request from: raul castanon ground work on floor drain and vent in wall test ok ok to cover
|
Plumbing Rough-in | 12/17/2008 | 12/17/2008 | 12/17/2008 | P | PART |
Jim Johnson
|
|
|
Phone #: ###-#### Internet Inspection Request from: raul castanon in wall rough-in on east side building in lab area test ok
|
Plumbing Rough-in | 12/10/2008 | 12/10/2008 | 12/10/2008 | A | PART |
Jim Johnson
|
|
|
Phone #: ###-#### Internet Inspection Request from: raul castanon rough-in on middle of building west side test ok
|
Groundwork | 12/8/2008 | 12/8/2008 | 12/8/2008 | P | CANC |
Jim Johnson
|
|
|
Partial GW only. Phone #: ###-#### Internet Inspection Request from: raul castanon canc
|
Plumbing Rough-in | 12/3/2008 | 12/4/2008 | 12/4/2008 | A | PART |
Jim Johnson
|
|
|
rough-in in area A test ok ok to cover
|
Plumbing Rough-in | 12/3/2008 | 12/3/2008 | 12/3/2008 | P | FAIL |
Jim Johnson
|
|
|
Phone #: ###-#### Internet Inspection Request from: raul castanon test failed on D W V need to correct leak,s and retest need additional hanger,s on overhead water as per table 3-2 upc 2003
|
Groundwork | 12/2/2008 | 12/3/2008 | 12/3/2008 | A | PART |
Jim Johnson
|
|
|
Phone #: ###-#### Internet Inspection Request from: raul castanon ground work in south east corner test ok
|
Groundwork | 11/19/2008 | 11/19/2008 | 11/19/2008 | P | PART |
Jim Johnson
|
|
|
Phone #: ###-#### Internet Inspection Request from: raul castanon existing plumbing in south-east corner capped off ok
|
Groundwork | 10/14/2008 | 10/14/2008 | 10/14/2008 | P | PASS |
Jim Johnson
|
|
|
casey Phone #: ###-####
|
Groundwork | 10/10/2008 | 10/10/2008 | 10/10/2008 | P | FAIL |
Eric Strole
|
|
|
Partial. Phone #: ###-#### Internet Inspection Request from: raul castanon-dwv test failed, do not cover.
|
Groundwork | 10/9/2008 | 10/10/2008 | 10/10/2008 | A | NR |
Eric Strole
|
|
|
Phone #: ###-#### Internet Inspection Request from: raul castanon
|
Groundwork | 10/9/2008 | 10/9/2008 | 10/9/2008 | P | PART |
Eric Strole
|
|
|
partial Phone #: ###-#### Internet Inspection Request from: raul castanon-sections of groundwork complete are marked on plans
|