Final | 5/24/2010 | 5/25/2010 | 5/25/2010 | A | PASS |
Jim Johnson
|
|
|
ken Phone #: ###-####
|
PLM-Aging Inspection | 5/13/2010 | 5/13/2010 | 5/13/2010 | | PASS |
Jim Johnson
|
|
|
called contractor project still under construction
|
Plumbing Rough-in | 11/17/2009 | 11/17/2009 | 11/17/2009 | P | PASS |
Jim Johnson
|
|
|
Ken-Please call prior to inspection Phone #: ###-####
|
Plumbing Rough-in | 10/16/2009 | 10/16/2009 | 10/16/2009 | P | PART |
Jim Johnson
|
|
|
sewer line to new addition test ok
|
Plumbing Rough-in | 10/16/2009 | 10/16/2009 | 10/16/2009 | P | PART |
Jim Johnson
|
|
|
Ken Phone #: ###-#### ground work D W V noted on approved set of plan,s test ok ok to cover
|