Permit Information
Permit NumberPLM10-02263
StatusCOL
Name PROFESSIONAL CONTRACTORS & ASSOCIAT
Site Address 101 S CAPITOL BLVD
Project Name 
Customer Number447-9271
ePlanReviewNo
Description
Plumbing Permit - New: 20th floor men and woman restroom upgrade to ADA compliance. toilets, sinks, floor drains, drinking fountain.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Water and/or Sewer10/31/201011/1/201011/2/2010APEND
DetailsLee Rice
pressure test to new waste piping. Note testing is only for the new piping install by us. not existing floor drain piping. we only installed the floor drains to existing pipe. >> Inspection requested via web by john hardy....called John and left message about verification of his state plumbing and mechanical license status and told him to call me back about this and this inspection.
Plumbing Rough-in10/29/201010/29/201010/29/2010AFAIL
DetailsDaryl Spivey
test on drinking fountain drain and vent failed and the other new waste and vent piping installed was not under test as required on correction notice........ds
Water and/or Sewer10/28/201010/29/201010/29/2010ACANC
DetailsDaryl Spivey
pressure test and change request as per thursday inspection >> Inspection requested via web by john hardy
not a sewer and water..............inspection for rough in............ds
Water and/or Sewer10/28/201010/28/201010/28/2010PFAIL
DetailsDaryl Spivey
Late pm inspection after 3:15 so that I can attend. ###-#### >> Inspection requested via web by john hardy
womens side floor drain not graded to drain, needs D/F horizontal vent supported per code, need a test on all new piping.........ds
Plumbing Rough-in10/25/201010/26/201010/26/2010ADONE
DetailsDaryl Spivey
Correction notice made and posted......ds
Water and/or Sewer10/24/201010/25/201010/25/2010PCANC
DetailsDaryl Spivey
pm inspection. request different inspector. will call again to speak with department head. final for 18th floor. work was done on the 17th floor ceiling space. Phone #: ###-#### >> Inspection requested via web by john hardy
Plumbing Rough-in10/25/201010/25/201010/25/2010PFAIL
DetailsDaryl Spivey
new piping needs to be tested, installed per 2003 UPC code with hangers and supports and graded to drain as noted on correction notice..............................ds
Plumbing Rough-in10/22/201010/22/201010/22/2010PDONE
DetailsDaryl Spivey
3 pm meeting with Liz, the property mgr, Duane and Sam, the maint. supervisors, John Hardy and myself. Liz had some issues with permit for 1801 that was pulled by Eight West Plg. At end of meeting John, Sam, duane and I went up to 20th floor to address issues on plumbing..........ds
Plumbing Rough-in10/21/201010/22/201010/22/2010AFAIL
DetailsDaryl Spivey
access to 20th floor by building owner. 3rd floor Unico Properties are by call Duane ###-#### or Sam ###-#### Phone #: ###-#### >> Inspection requested via web by john hardy
waste and water piping needs to be supported better,..meeting at 3 pm.............ds